Anchor Residency, Ghatkopar West

Lapsed

by Anchor Sky Scrapers LLP · Ghatkopar West, Mumbai 400086 · Map

Launched
Jul 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Dec 2021Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
18
2 BHK
36
Other units
5
Total units
59
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 70%Dec 2025: Final finishes 70%Jul 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%–
100%100%70%–
100%100%70%43

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400086

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400086
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths3 yrs 4 mths
Possession date extendedBy 2 yrs5 of 6
Possession date (MahaRERA)Dec 2021Dec 2024
Concrete structure (RCC)100%100%
Units booked–54%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Anchor Residency by Anchor Sky Scrapers LLP is a 59-unit project in Ghatkopar West, Mumbai 400086, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Anchor Residency is a project by Anchor Sky Scrapers LLP in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800001059. It was launched in July 2017. It has 59 units in 2 buildings: 54 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2021, after an extension of 2 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.