- Launched
- Aug 20175 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 3 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 6 of 1250% · 6 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 12 units
Rehab6 units for existing members
Total 18 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 8
- 3 BHK
- 9
- Total units
- 18
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 12
- Rehab units
- 6
- Reserved units
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 6 | |
| 100% | 85% | 0% | 6 | |
| 100% | 85% | 0% | 7 | |
| 100% | 85% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400014
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 3 yrs 1 mth |
| Possession date extended | By 3 yrs 6 mths | 1 of 3 |
| Possession date (MahaRERA) | Jun 2026 | Apr 2023 |
| Concrete structure (RCC) | 100% | 90% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- LS Laxmi Sadan, Dadar East
- Govind Niwas, Dadar East
- Spenta Nest, Dadar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| LS Laxmi Sadan | August 2017 | September 2020 | 90% | 10 units booked out of total 12 units |
| Govind Niwas | September 2017 | April 2023 | 0% | 9 units booked out of total 15 units |
| Spenta Nest | September 2017 | December 2028 | 100% | – |
About this project
63 Elegance by Siddharth Developers is an 18-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in August 2017; its MahaRERA registration has lapsed. 6 units booked out of 12 units for sale. The concrete structure (RCC) is complete.
Read full summary
63 Elegance is a BMC-sanctioned project by Siddharth Developers in Dadar East, Mumbai 400014, registered with MahaRERA as P51800009011. It was launched in August 2017. It has 18 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 18 units, 12 are for sale and 6 are rehab units for existing members.
Possession was due in June 2026, after an extension of 3 years 6 months from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.
6 units booked out of 12 units for sale (50%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 85% to 100% and the possession date has moved from March 2025 to June 2026.