Govind Niwas, Dadar East

Lapsed

by Shree Sai Datta Developers · Dadar East, Mumbai 400014 · Map

Launched
Sep 20171 yr 9 mths originally promised
Possession (MahaRERA)
Apr 2023Extended by 3 yrs 10 mthsWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
9 of 1560%
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
9
2 BHK
3
3 BHK
3
Total units
15
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%9
100%0%0%–
100%0%0%–
100%0%0%9

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400014

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400014
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 9 mths5 yrs 4 mths
Possession date extendedBy 3 yrs 10 mths1 of 3
Possession date (MahaRERA)Apr 2023Jun 2026
Concrete structure (RCC)0%100%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Govind Niwas by Shree Sai Datta Developers is a 15-unit project in Dadar East, Mumbai 400014, launched in September 2017; its MahaRERA registration has lapsed. 9 units booked out of total 15 units. Work on the concrete structure (RCC) has not started.

Read full summary

Govind Niwas is a project by Shree Sai Datta Developers in Dadar East, Mumbai 400014, registered with MahaRERA as P51900012407. It was launched in September 2017. It has 15 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in April 2023, after an extension of 3 years 10 months from the original June 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

9 units booked out of total 15 units (60%).