Sagar Avenue II G, Santacruz East
Lapsed
by Sagar Shopping Developers · Santacruz East, Mumbai 400055 · Map
- Launched
- Sep 20175 yrs 9 mths promised
- Possession (MahaRERA)
- Jun 2023Not extendedWhat does Lapsed mean?
- Concrete structure
- 57%Mid-construction
- Booked
- –
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 47
- Total units
- 47
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 57% | 20% | – | |
| 100% | 57% | 20% | – | |
| 100% | 57% | 20% | 16 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400055
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 9 mths | 3 yrs 7 mths |
| Possession date extended | No | 5 of 6 |
| Possession date (MahaRERA) | Jun 2023 | Jul 2023 |
| Concrete structure (RCC) | 57% | 92% |
| Units booked | – | 70% |
| MahaRERA complaints (filed by or against the builder) | 0 | 1 |
The 6 projects
- Rizvi Utopia, Santacruz East
- Silver heights, Santacruz East
- Rudra Paradise, Santacruz East
- Ekta Sra Chs, Santacruz East
- Om Jai Chsl - Augustus, Santacruz East
- Kolina, Santacruz East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rizvi Utopia | September 2017 | June 2022 | 97% | – |
| Silver heights | August 2017 | April 2028 | 88% | 43 units booked out of total 55 units |
| Rudra Paradise | August 2017 | July 2026 | 100% | 28 units booked out of 46 units for sale |
| Ekta Sra Chs | August 2017 | July 2024 | 100% | 23 units booked out of 27 units for sale |
| Om Jai Chsl - Augustus | August 2017 | December 2020 | 0% | 14 units booked out of total 23 units |
| Kolina | August 2017 | January 2022 | 40% | – |
About this project
Sagar Avenue II G by Sagar Shopping Developers is a 47-unit project in Santacruz East, Mumbai 400055, launched in September 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 57% complete.
Read full summary
Sagar Avenue II G is a project by Sagar Shopping Developers in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800012801. It was launched in September 2017. It has 47 units in 1 building, with 1 RK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 57% complete, final finishes 20% complete.