Ekta Sra Chs, Santacruz East

Ready to moveLapsed

by Classic Enterprises Vakola · Santacruz East, Mumbai 400055 · Map

Launched
Aug 20176 yrs originally promised
Possession (MahaRERA)
Jul 2024Extended by 11 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
23 of 2785% · 43 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale23 booked out of 27 units

Rehab43 units for existing members

Total 70 units. Rehab units are not for sale.

Project facts

1 BHK
53
2 BHK
6
Other units
11
Total units
70
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
27
Rehab units
43

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 10%Dec 2025: Final finishes 60%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%23
100%100%60%22
100%100%10%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400055

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400055
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs4 yrs 8 mths
Possession date extendedBy 11 mths5 of 6
Possession date (MahaRERA)Jul 2024Dec 2025
Concrete structure (RCC)100%92%
Units booked (free sale)85%70%
MahaRERA complaints (filed by or against the builder)02

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ekta Sra Chs by Classic Enterprises Vakola is a 70-unit SRA-sanctioned project in Santacruz East, Mumbai 400055, launched in August 2017; its MahaRERA registration has lapsed. 23 units booked out of 27 units for sale. The concrete structure (RCC) is complete.

Read full summary

Ekta Sra Chs is an SRA-sanctioned project by Classic Enterprises Vakola in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800004680. It was launched in August 2017. It has 70 units in 1 building: 59 homes (1 and 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 70 units, 27 are for sale and 43 are rehab units for existing members.

Possession was due in July 2024, after an extension of 11 months from the original August 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

23 units booked out of 27 units for sale (85%).