Peak 25, Vikhroli

Ready to moveLapsed

by Vlkrishnapingaksha Developers LLP · Vikhroli, Mumbai 400083 · Map

Launched
Jan 20223 yrs 11 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
85 of 8897% · 21 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale85 booked out of 88 units

Rehab21 units for existing members

Total 109 units. Rehab units are not for sale.

Project facts

1 BHK
65
2 BHK
23
3 BHK
21
Total units
109
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
88
Rehab units
21

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jul 2026Oct 2026Dec 2024: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%85
0%0%0%85
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400083

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths4 yrs 1 mth
Possession date extendedNo3 of 6
Possession date (MahaRERA)Dec 2025Jun 2026
Concrete structure (RCC)100%100%
Units booked (free sale)97%93%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Peak 25 by Vlkrishnapingaksha Developers LLP is a 109-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in January 2022; its MahaRERA registration has lapsed. 85 units booked out of 88 units for sale. The concrete structure (RCC) is complete.

Read full summary

Peak 25 is a MHADA-sanctioned project by Vlkrishnapingaksha Developers LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800032526. It was launched in January 2022. It has 109 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 109 units, 88 are for sale and 21 are rehab units for existing members.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

85 units booked out of 88 units for sale (97%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100%.