Shraddha Prominent, Vikhroli
by Shraddha Landmark Private Limited · Vikhroli, Mumbai 400083 · Map
- Launched
- Jun 20223 yrs 6 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 66 of 7193% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale66 booked out of 71 units
Rehab16 units for existing members
Total 87 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 62
- 2 BHK
- 22
- 3 BHK
- 1
- Total units
- 87
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 71
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 66 | |
| 100% | 100% | 0% | 65 | |
| 100% | 93% | 0% | 62 | |
| 100% | 55% | 0% | 25 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400083
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 3 yrs 10 mths |
| Possession date extended | By 1 yr | 1 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Jan 2026 |
| Concrete structure (RCC) | 100% | 87% |
| Units booked (free sale) | 93% | 95% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Adishakti Chs Adityaraj Prime, Vikhroli
- Vista Meadows, Vikhroli
- Puneet Brahmand, Vikhroli
- Puneet Amarjyoti, Vikhroli
- Peak 25, Vikhroli
- Star Right Heights, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Adishakti Chs Adityaraj Prime | June 2022 | March 2026 | 91% | 143 units booked out of total 152 units |
| Vista Meadows | August 2022 | December 2025 | 100% | 87 units booked out of total 99 units |
| Puneet Brahmand | September 2022 | December 2026 | 54% | 106 units booked out of total 106 units |
| Puneet Amarjyoti | September 2022 | December 2026 | 83% | 54 units booked out of total 54 units |
| Peak 25 | January 2022 | December 2025 | 100% | 85 units booked out of 88 units for sale |
| Star Right Heights | January 2022 | March 2025 | 0% | 46 units booked out of total 50 units |
About this project
Shraddha Prominent by Shraddha Landmark Private Limited is an 87-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in June 2022 with possession due in December 2026. 66 units booked out of 71 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shraddha Prominent is a MHADA-sanctioned project by Shraddha Landmark Private Limited in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800046232. It was launched in June 2022. It has 87 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 87 units, 71 are for sale and 16 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.
66 units booked out of 71 units for sale (93%). Since the July 2026 update, 1 more unit has been booked.
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.