Corinthia, Bhandup West

by Lodha Developers Limited · Bhandup West, Mumbai 400078 · Map

Launched
Oct 2024First of 3 phases
Possession (MahaRERA)
May 2031 – Nov 2031Extended in all 3 phases
Concrete structure
39%Weighted across 3 phases
Booked
346 of 62156% · 318 in Jul 2026
Buildings
46.9 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
5
2 BHK
241
3 BHK
370
4 BHK
5
Total units
621
Buildings
4
Land
6.9 acres
Phases
3
MahaRERA complaints
1

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Corinthia -Tower 1 and Tower 2
Mid-construction
PR118000240002231357%54%
Corinthia Tower - 5
Mid-construction
PR118000240004315223%63%
Corinthia-Tower 6
Mid-construction
PR118000240004415618%53%
Show updates by phase

Corinthia -Tower 1 and Tower 2 (PR1180002400022)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%57%0%168
100%22%0%161
0%0%0%126
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Corinthia Tower - 5 (PR1180002400043)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%23%0%96
100%9%0%75
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Corinthia-Tower 6 (PR1180002400044)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%18%0%82
100%12%0%82
100%0%0%48
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)39%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 25%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 16%Oct 2026: Concrete structure (RCC) 39%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 39%Final finishes 0%

How to read construction stages

Compared with 3 similar projects in PIN 400078

Projects with 300–1,300 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 8 mths5 yrs
Possession date extendedYes1 of 3
Possession date (MahaRERA)May 2031 – Nov 2031Nov 2029
Concrete structure (RCC)39%12%
Units booked56%69%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Corinthia by Lodha Developers Limited is a 621-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 3 phases, with possession dates from May 2031 to November 2031. 346 units booked out of total 621 units. The concrete structure (RCC) is 39% complete.

Read full summary

Corinthia is a BMC-sanctioned project by Lodha Developers Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as 3 phases (PR1180002400022, PR1180002400043, PR1180002400044). The first phase was launched in October 2024. Together the phases have 621 units in 4 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from May 2031 to November 2031; all 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 39% complete and final finishes 0% complete. None of the 3 phases has its structure complete.

346 units booked out of total 621 units (56%). Since the July 2026 update, 28 more units have been booked.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →