Corinthia, Bhandup West
by Lodha Developers Limited · Bhandup West, Mumbai 400078 · Map
- Launched
- Oct 2024First of 3 phases
- Possession (MahaRERA)
- May 2031 – Nov 2031Extended in all 3 phases
- Concrete structure
- 39%Weighted across 3 phases
- Booked
- 346 of 62156% · 318 in Jul 2026
- Buildings
- 46.9 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 5
- 2 BHK
- 241
- 3 BHK
- 370
- 4 BHK
- 5
- Total units
- 621
- Buildings
- 4
- Land
- 6.9 acres
- Phases
- 3
- MahaRERA complaints
- 1
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Corinthia -Tower 1 and Tower 2 Mid-construction | PR1180002400022 | 313 | 57% | 54% | |
| Corinthia Tower - 5 Mid-construction | PR1180002400043 | 152 | 23% | 63% | |
| Corinthia-Tower 6 Mid-construction | PR1180002400044 | 156 | 18% | 53% |
Show updates by phase
Corinthia -Tower 1 and Tower 2 (PR1180002400022)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 57% | 0% | 168 | |
| 100% | 22% | 0% | 161 | |
| 0% | 0% | 0% | 126 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Corinthia Tower - 5 (PR1180002400043)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 23% | 0% | 96 | |
| 100% | 9% | 0% | 75 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Corinthia-Tower 6 (PR1180002400044)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 18% | 0% | 82 | |
| 100% | 12% | 0% | 82 | |
| 100% | 0% | 0% | 48 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 3 similar projects in PIN 400078
Projects with 300–1,300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 8 mths | 5 yrs |
| Possession date extended | Yes | 1 of 3 |
| Possession date (MahaRERA) | May 2031 – Nov 2031 | Nov 2029 |
| Concrete structure (RCC) | 39% | 12% |
| Units booked | 56% | 69% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 3 projects
- Arkade Rare, Bhandup West
- Raheja Antares, Bhandup West
- Godrej Nurture, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Arkade Rare | August 2024 | December 2028 | 69% | 333 units booked out of total 479 units |
| Raheja Antares | August 2024 | Nov 2029 | 12% | 333 units booked out of total 485 units |
| Godrej Nurture | July 2024 | Mar 2032 – Jul 2032 | 0% | 310 units booked out of total 616 units |
About this project
Corinthia by Lodha Developers Limited is a 621-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 3 phases, with possession dates from May 2031 to November 2031. 346 units booked out of total 621 units. The concrete structure (RCC) is 39% complete.
Read full summary
Corinthia is a BMC-sanctioned project by Lodha Developers Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as 3 phases (PR1180002400022, PR1180002400043, PR1180002400044). The first phase was launched in October 2024. Together the phases have 621 units in 4 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.
The phases' registered possession dates run from May 2031 to November 2031; all 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 39% complete and final finishes 0% complete. None of the 3 phases has its structure complete.
346 units booked out of total 621 units (56%). Since the July 2026 update, 28 more units have been booked.
Lodha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
| Completed without extending the possession date | 31 |
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.