Mpr Shri Paras Darshan, Kandivali West
by Mpr Group · Kandivali West, Mumbai 400067 · Map
- Launched
- May 20252 yrs 9 mths promised
- Possession (MahaRERA)
- Feb 2028Not extended
- Concrete structure
- 53%Mid-construction
- Booked (free sale)
- 10 of 2540% · 24 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 25 units
Rehab24 units for existing members
Land-owner share4 units, not for sale
Total 53 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 2
- 2 BHK
- 24
- 3 BHK
- 14
- Other units
- 13
- Total units
- 53
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 25
- Rehab units
- 24
- Land-owner share (not for sale)
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 53% | 0% | 10 | |
| 100% | 24% | 0% | 9 | |
| 100% | 0% | 0% | 7 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 20–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Feb 2028 | Mar 2028 |
| Concrete structure (RCC) | 53% | 31% |
| Units booked (free sale) | 40% | 38% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Vencon Bhagat Niwas, Kandivali West
- Triratna, Kandivali West
- Aashray, Kandivali West
- Om Shri Ganesh CHS LTD, Kandivali West
- Rudra, Kandivali West
- Jay Co-Operative Housing Society Limited, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vencon Bhagat Niwas | May 2025 | December 2027 | 63% | 13 units booked out of 39 units for sale |
| Triratna | May 2025 | June 2028 | 27% | 14 units booked out of 38 units for sale |
| Aashray | April 2025 | December 2027 | 35% | 0 units booked out of 7 units for sale |
| Om Shri Ganesh CHS LTD | March 2025 | December 2026 | 100% | 17 units booked out of total 29 units |
| Rudra | August 2025 | December 2029 | 19% | 10 units booked out of 22 units for sale |
| Jay Co-Operative Housing Society Limited | October 2025 | December 2028 | 0% | 6 units booked out of 15 units for sale |
About this project
Mpr Shri Paras Darshan by Mpr Group is a 53-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in May 2025 with possession due in February 2028. 10 units booked out of 25 units for sale. The concrete structure (RCC) is 53% complete.
Read full summary
Mpr Shri Paras Darshan is a BMC-sanctioned project by Mpr Group in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800080359. It was launched in May 2025. It has 53 units in 1 building: 40 homes (1, 2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 53 units, 25 are for sale, 24 are rehab units for existing members and 4 are the land-owner's share, not for sale.
Its registered possession date is February 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 53% complete, final finishes not started.
10 units booked out of 25 units for sale (40%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 24% to 53%.