Vencon Bhagat Niwas, Kandivali West

by Vencon Realty And Infrastructure LLP · Kandivali West, Mumbai 400067 · Map

Launched
May 20252 yrs 7 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
63%Mid-construction
Booked (free sale)
13 of 3933% · 26 rehab units
Buildings
30.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 39 units

Rehab26 units for existing members

Total 65 units. Rehab units are not for sale.

Project facts

1 BHK
26
2 BHK
17
Other units
22
Total units
65
Buildings
3
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
39
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)63%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 33%Jul 2026: Concrete structure (RCC) 63%Oct 2026: Concrete structure (RCC) 63%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 63%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%63%0%13
100%63%0%13
100%33%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 7 mths2 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Apr 2028
Concrete structure (RCC)63%31%
Units booked (free sale)33%42%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vencon Bhagat Niwas by Vencon Realty And Infrastructure LLP is a 65-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in May 2025 with possession due in December 2027. 13 units booked out of 39 units for sale. The concrete structure (RCC) is 63% complete.

Read full summary

Vencon Bhagat Niwas is a BMC-sanctioned project by Vencon Realty And Infrastructure LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800080226. It was launched in May 2025. It has 65 units in 3 buildings: 43 homes (1 and 2 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 65 units, 39 are for sale and 26 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 63% complete, final finishes not started.

13 units booked out of 39 units for sale (33%).