Skip to main content

Triratna, Kandivali West

by Charkop Triratna Co-Operative Housing Society Limited · Kandivali West, Mumbai 400067 · Map

Launched
May 20253 yrs 1 mth promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
27%Mid-construction
Booked (free sale)
14 of 3837% · 27 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 38 units

Rehab27 units for existing members

Total 65 units. Rehab units are not for sale.

Project facts

1 BHK
16
2 BHK
18
3 BHK
25
Other units
6
Total units
65
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
38
Rehab units
27

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)27%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 9%Oct 2026: Concrete structure (RCC) 27%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 27%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%27%0%14
100%9%0%11
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth2 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2028Jan 2028
Concrete structure (RCC)27%44%
Units booked (free sale)37%42%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Triratna by Charkop Triratna Co-Operative Housing Society Limited is a 65-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in May 2025 with possession due in June 2028. 14 units booked out of 38 units for sale. The concrete structure (RCC) is 27% complete.

Read full summary

Triratna is a MHADA-sanctioned project by Charkop Triratna Co-Operative Housing Society Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800080334. It was launched in May 2025. It has 65 units in 1 building: 59 homes (1, 2 and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 65 units, 38 are for sale and 27 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 27% complete, final finishes not started.

14 units booked out of 38 units for sale (37%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 9% to 27%.