Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71, Chembur

Ready to moveLapsed

by G A Builders Pvt Ltd · Chembur, Mumbai 400071 · Map

Launched
Aug 20173 yrs 5 mths promised
Possession (MahaRERA)
Jan 2021Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
204 of 20998%
Buildings
11.6 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
120
3 BHK
87
5+ BHK
1
Other units
1
Total units
209
Buildings
1
Land
1.6 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services93%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 93%Dec 2025: Final finishes 93%Jul 2026: Final finishes 93%Oct 2026: Final finishes 93%Excavation 100%Concrete structure (RCC) 100%Final finishes 93%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%93%204
100%100%93%–
100%100%93%–
100%100%93%204

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths5 yrs 4 mths
Possession date extendedNo5 of 6
Possession date (MahaRERA)Jan 2021Nov 2025
Concrete structure (RCC)100%88%
Units booked98%92%
MahaRERA complaints (filed by or against the builder)17

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71 by G A Builders Pvt Ltd is a 209-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. 204 units booked out of total 209 units. The concrete structure (RCC) is complete.

Read full summary

Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71 is a BMC-sanctioned project by G A Builders Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800009310. It was launched in August 2017. It has 209 units in 1 building: 208 homes (2, 3 and 5+ BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in January 2021. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 93% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

204 units booked out of total 209 units (98%).