Dk Residency, Mumbai Central
Lapsed
by Dk Construction Builder And Land Developer · Mumbai Central, Mumbai 400008 · Map
- Launched
- Aug 20172 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2021Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 23%Mid-construction
- Booked
- –
- Buildings
- 10.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 85
- 3 BHK
- 2
- Other units
- 3
- Total units
- 90
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 23% | 90% | – | |
| 100% | 23% | 90% | – | |
| 100% | 23% | 90% | – | |
| 100% | 23% | 90% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400008
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 4 mths | 5 yrs 4 mths |
| Possession date extended | By 2 yrs | 4 of 6 |
| Possession date (MahaRERA) | Dec 2021 | Aug 2026 |
| Concrete structure (RCC) | 23% | 68% |
| Units booked | – | 38% |
| MahaRERA complaints (filed by or against the builder) | 1 | 1 |
The 6 projects
- La Mer Residences, Mumbai Central
- Baug E Umar, Mumbai Central
- Ekdant, Mumbai Central
- Lakadawala Heights, Mumbai Central
- Ndw The Crest, Mumbai Central
- Dudhwala Aquapearl, Mumbai Central
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| La Mer Residences | August 2017 | December 2030 | 45% | 77 units booked out of 201 units for sale |
| Baug E Umar | August 2017 | April 2027 | 0% | 13 units booked out of 31 units for sale |
| Ekdant | August 2017 | July 2024 | 100% | – |
| Lakadawala Heights | August 2017 | April 2027 | 0% | 6 units booked out of total 114 units |
| Ndw The Crest | August 2017 | December 2025 | 90% | – |
| Dudhwala Aquapearl | August 2017 | December 2022 | 100% | – |
About this project
Dk Residency by Dk Construction Builder And Land Developer is a 90-unit project in Mumbai Central, Mumbai 400008, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 23% complete.
Read full summary
Dk Residency is a project by Dk Construction Builder And Land Developer in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900004951. It was launched in August 2017. It has 90 units in 1 building: 87 homes (1 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2021, after an extension of 2 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 23% complete, final finishes 90% complete.