Pearl Bay View, Dadar West

by Pearl Concept Constructions · Dadar West, Mumbai 400028 · Map

Launched
Oct 20224 yrs 2 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
8 of 1844% · 18 rehab units
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 18 units

Rehab18 units for existing members

Total 36 units. Rehab units are not for sale.

Project facts

1 BHK
4
2 BHK
23
3 BHK
3
5+ BHK
1
Other units
5
Total units
36
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1
Free-sale units
18
Rehab units
18

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services11%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 6%Dec 2025: Final finishes 19%Jul 2026: Final finishes 11%Oct 2026: Final finishes 11%Excavation 100%Concrete structure (RCC) 100%Final finishes 11%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%11%8
100%100%11%8
100%100%19%–
100%100%6%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400028

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths3 yrs 8 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)100%70%
Units booked (free sale)44%51%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pearl Bay View by Pearl Concept Constructions is a 36-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in October 2022 with possession due in December 2026. 8 units booked out of 18 units for sale. The concrete structure (RCC) is complete.

Read full summary

Pearl Bay View is a BMC-sanctioned project by Pearl Concept Constructions in Dadar West, Mumbai 400028, registered with MahaRERA as P51900047085. It was launched in October 2022. It has 36 units in 1 building: 31 homes (1, 2, 3 and 5+ BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 18 are for sale and 18 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 11% complete.

8 units booked out of 18 units for sale (44%).