Serene Bay, Dadar West
by Shubha Gruha · Dadar West, Mumbai 400028 · Map
- Launched
- Sep 20223 yrs 9 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr 6 mths
- Concrete structure
- 50%Mid-construction
- Booked (free sale)
- 7 of 1164% · 17 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 11 units
Rehab17 units for existing members
Land-owner share2 units, not for sale
Total 30 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 13
- 1 BHK
- 5
- 3 BHK
- 6
- 4 BHK
- 6
- Total units
- 30
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 11
- Rehab units
- 17
- Land-owner share (not for sale)
- 2
- Reserved units
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 75% | 7 | |
| 100% | 50% | 75% | 5 | |
| 100% | 50% | 75% | 5 | |
| 100% | 0% | 10% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400028
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs 9 mths |
| Possession date extended | By 1 yr 6 mths | 2 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2026 |
| Concrete structure (RCC) | 50% | 95% |
| Units booked (free sale) | 64% | 47% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Amaresha, Dadar West
- Pearl Bay View, Dadar West
- The Pavilion, Dadar West
- 1891 Ekam Parkk, Dadar West
- Shree Sai Arti, Dadar West
- Amara, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Amaresha | September 2022 | September 2029 | 0% | 3 units booked out of 21 units for sale |
| Pearl Bay View | October 2022 | December 2026 | 100% | 8 units booked out of 18 units for sale |
| The Pavilion | December 2022 | December 2025 | 90% | 16 units booked out of total 25 units |
| 1891 Ekam Parkk | June 2022 | December 2026 | 100% | 18 units booked out of 34 units for sale |
| Shree Sai Arti | January 2023 | December 2026 | 100% | 6 units booked out of total 23 units |
| Amara | February 2023 | December 2026 | 0% | 11 units booked out of 22 units for sale |
About this project
Serene Bay by Shubha Gruha is a 30-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in September 2022 with possession due in December 2027. 7 units booked out of 11 units for sale. The concrete structure (RCC) is 50% complete.
Read full summary
Serene Bay is a BMC-sanctioned project by Shubha Gruha in Dadar West, Mumbai 400028, registered with MahaRERA as P51900047047. It was launched in September 2022. It has 30 units in 1 building, with 1 RK, 1 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 11 are for sale, 17 are rehab units for existing members and 2 are the land-owner's share, not for sale.
Its registered possession date is December 2027, extended by 1 year 6 months from the original June 2026. Construction: excavation complete, structure (RCC) 50% complete, final finishes 75% complete.
7 units booked out of 11 units for sale (64%). Since the July 2026 update, 2 more units have been booked and the possession date has moved from June 2026 to December 2027.