Skip to main content

Amaresha, Dadar West

by Inconel Developers & Builders Private Limited · Dadar West, Mumbai 400028 · Map

Launched
Sep 20223 yrs 8 mths originally promised
Possession (MahaRERA)
Sep 2029Extended by 3 yrs 4 mths
Concrete structure
0%Early stage
Booked (free sale)
3 of 2114% · 26 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 21 units

Rehab26 units for existing members

Total 47 units. Rehab units are not for sale.

Project facts

1 BHK
21
2 BHK
23
Other units
3
Total units
47
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
21
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 95%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%3
100%0%0%3
95%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400028

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 10 mths
Possession date extendedBy 3 yrs 4 mths2 of 6
Possession date (MahaRERA)Sep 2029Dec 2026
Concrete structure (RCC)0%95%
Units booked (free sale)14%51%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Amaresha by Inconel Developers & Builders Private Limited is a 47-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in September 2022 with possession due in September 2029. 3 units booked out of 21 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Amaresha is a BMC-sanctioned project by Inconel Developers & Builders Private Limited in Dadar West, Mumbai 400028, registered with MahaRERA as P51900046922. It was launched in September 2022. It has 47 units in 1 building: 44 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 21 are for sale and 26 are rehab units for existing members.

Its registered possession date is September 2029, extended by 3 years 4 months from the original May 2026. Construction: excavation complete, structure (RCC) not started, final finishes not started.

3 units booked out of 21 units for sale (14%).