Ranjekar projects in Pune

MahaRERA projects by Ranjekar registered 2017–2026 in Pune & PCMC.

Projects registered with MahaRERA27
Total units across these projects806
Full record

MahaRERA projects registered 2017–2026 in Pune & PCMC

Completed without extending the possession date10
Completed after an extension4
Lapsed0
Under construction13
Possession date extended on the builder's application7
Typical time from launch to 100% structure2 years 10 months
MahaRERA complaints (filed by or against the builder), all Ranjekar projects0 (0 of 27 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Kothrud (11) · Erandwane (5) · Parvati (2) · Shivajinagar (1) · Karve Nagar (1) · Aundh (1)

Under construction

ProjectVillageStagePossessionBooked
Anupam Heights Cooperative Housing Society LimitedKothrudMid-constructionMay 202832 units booked out of total 57 units
AuraParvatiNearing possessionOctober 20268 units booked out of total 18 units
AvantikaKothrudNearing possessionDecember 202636 units booked out of total 52 units
DhanasampadaErandwaneNearing possessionMarch 202738 units booked out of total 46 units
DhanashreeAundhEarly stageOctober 202818 units booked out of total 26 units
MadhughatErandwaneEarly stageJanuary 20300 units booked out of total 2 units
RakhiKothrudEarly stageOctober 202816 units booked out of total 34 units
SaukhyamKothrudNearing possessionApril 20278 units booked out of total 11 units
ShreejiErandwaneEarly stageDecember 20286 units booked out of total 12 units
Snehabhavan Cooperative Housing Society LimitedErandwaneNearing possessionMarch 202811 units booked out of total 16 units
TirthKothrudMid-constructionMarch 202857 units booked out of total 72 units
Umashankar PrasadKothrudMid-constructionFebruary 202869 units booked out of total 109 units
VasundharaKothrudMid-constructionDecember 202668 units booked out of total 103 units
Completed
ProjectVillageStatus
AmeyKothrudCompleted
AnantParvatiCompleted
BhagyashreeKothrudCompleted
DrumadalShivajinagarCompleted
JagdeepErandwaneCompleted
MeghmanasAundhCompleted
MeghrajshreeKothrudCompleted
OmkarKarve NagarCompleted
Punyaee Business SquareKothrudCompleted
RatnankurKothrudCompleted
ShivrangSadashiv PethCompleted
SnehdeepParvatiCompleted
UmangParvatiCompleted
YashKothrudCompleted

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.