Skip to main content
← Back

Dhanasampada, Erandwane

by Ranjekar Realty LLP. Erandwane, Pune 411004. View on Google Maps

Launched
2 years 6 months originally promised
Possession date (MahaRERA)
5 months awayExtended by 1 year (originally March 2026). Why possession dates change
Concrete structure (RCC)
100%Nearing possession
Units booked
20 of 4643% booked
Price per sq ft (incl. balconies and terrace)
₹18,1002025 · 10 sales80% of the 2025 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK1
2 BHK25
3 BHK20
Total units46
Buildings1
Land0.3 acres
Landowner share17
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 7 → 20 · structure 0% → 100% · possession date March 2026 → March 2027

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹18,100 per sq ft10 sales

Rate vs other Erandwane projects, 2025: about 5% lower

Compared with 6 similar projects in PIN 411004

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411004
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 6 mths2 yrs 8 mths
Possession date extendedBy 1 year2 of 6
Possession date (MahaRERA)March 2027September 2026
Concrete structure (RCC) complete100%100%
Share of units booked43%40%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 6 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%20
100%0%0%7
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Dhanasampada (MahaRERA P52100052758) is a residential project by Ranjekar Realty LLP in Erandwane, Pune 411004. It was launched in September 2023. It has 46 units in 1 building, with 1 RK, 2 BHK & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.

20 of its 46 units are booked (43%). Since the December 2025 update, 13 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from March 2026 to March 2027. 80% of the 2025 sales we found here were at ₹18,100 per sq ft or less, counting balconies and terrace in the size, based on 10 registered sales. Buyers here paid a rate about 5% lower than at other Erandwane projects in 2025.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052758.Check it on MahaRERA (P52100052758)All projects in Deccan