Ravinanda projects in Pune

MahaRERA projects by Ravinanda registered 2017–2021 in Pune & PCMC.

Projects registered with MahaRERA10
Total units across these projects2,381
Full record

MahaRERA projects registered 2017–2021 in Pune & PCMC

Completed without extending the possession date0
Completed after an extension0
Lapsed1
Under construction4
Not updated on MahaRERA for over a year5
Possession date extended on the builder's application8
Typical time from launch to 100% structure5 years 9 months
MahaRERA complaints (filed by or against the builder), all Ravinanda projects106 (7 of 10 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
  • Not updated on MahaRERA for over a year: the builder has not filed an update with MahaRERA for more than a year, so FlatNama cannot show a current status.

Where they build: Wagholi (1) · Dhayari (1) · Kondhwa Khurd (1)

Under construction

ProjectVillageStagePossessionBooked
Ravinanda 37Kondhwa KhurdMid-constructionMarch 202774 units booked out of total 109 units
Ravinanda Aamrai · 2 phasesDhayariNearing possessionDec 2026 – Dec 2028300 units booked out of total 339 units
SkylightsWagholiMid-constructionJune 2027389 units booked out of total 479 units
Lapsed
ProjectVillageStatus
Sky WaterWagholiLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us