Triaa projects in Pune
MahaRERA projects by Triaa registered 2017–2026 in Pune & PCMC.
| Projects registered with MahaRERA | 11 |
|---|---|
| Total units across these projects | 2,307 |
Full record
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Completed without extending the possession date | 0 |
|---|---|
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 8 |
| Possession date extended on the builder's application | 6 |
| Typical time from launch to 100% structure | 2 years 11 months |
| MahaRERA complaints (filed by or against the builder), all Triaa projects | 4 (3 of 11 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Mundhwa (1) · Hinjewadi (1) · Dhanori (1) · Wagholi (1) · Mohammadwadi (1) · Lohegaon (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Kosmic Kourtyard Phase 2 | Wagholi | Mid-construction | December 2028 | 106 units booked out of total 130 units |
| Nesterra · 2 phases | Lohegaon | Mid-construction | Dec 2030 – Apr 2031 | 231 units booked out of total 676 units |
| One Aretha · 2 phases | Dhanori | Mid-construction | Dec 2028 – Apr 2029 | 232 units booked out of total 398 units |
| Rezo Phase 1 | Mohammadwadi | Mid-construction | December 2030 | 10 units booked out of total 86 units |
| Triaa Galaxy - Phase 1 | Hinjewadi | Mid-construction | June 2027 | 30 units booked out of total 111 units |
Lapsed
| Project | Village | Status |
|---|---|---|
| Elysia | Mundhwa | Lapsed |
| Kosmic Kourtyard | Wagholi | Lapsed |
| Triaa Hillome | Ghorpadi | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.