Tanishq Vlasta, Alandi Rural
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Tanishq Realities. Alandi Rural, Pune 412105. View on Google Maps
- Launched
- 5 years 5 months originally promised
- Possession date (MahaRERA)
- 2 years 10 months ago. No further extension recordedExtended by 1 year (originally December 2022). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stageAverage across 3 buildings
- Units booked
- 183 of 21784% booked
Project facts
| 1 BHK | 87 |
|---|---|
| 2 BHK | 130 |
| Total units | 217 |
| Buildings | 3 |
| Land | 5 acres |
| Complaints on MahaRERA (filed by or against the builder) | 14 |
Since Dec 2025: booked 178 → 183 · final finishes 95% → 100% · complaints 13 → 14
Compared with 4 similar projects in PIN 412105
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 5 mths | 3 yrs 4 mths |
| Possession date extended | By 1 year | 4 of 4 |
| Possession date passed | Yes, due December 2023 | 1 ready to move; 1 also past their date |
| Concrete structure (RCC) complete | 100% | 80% |
| Share of units booked | 84% | 48% |
| Complaints on MahaRERA (filed by or against the builder) | 14 | 2 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Dwarka Square Phase I | August 2017 | December 2023 | 60% | 139 of 262 booked (53%) |
| Suvarna Alay | August 2017 | December 2019 | 100% | All 118 units booked |
| Santiago Skymont | September 2017 | December 2030 | 33% | 59 of 142 booked (42%) |
| Dnyanvishwa | January 2018 | December 2030 | 100% | 85 of 239 booked (36%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 183 | |
| 100% | 100% | 95% | 178 | |
| 50% | 50% | 37% | 164 |
"—" means MahaRERA shows no figure for that update.
About this project
Tanishq Vlasta (MahaRERA P52100002155) is a residential project by Tanishq Realities in Alandi Rural, Pune 412105. It was launched in July 2017. It has 217 units in 3 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
183 of its 217 units are booked (84%). Since the December 2025 update, 5 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.