Suvarna Alay, Charholi Khurd
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Maheshwari Developers. Charholi Khurd, Pune 412105. View on Google Maps
- Launched
- 1 year 4 months originally promised
- Possession date (MahaRERA)
- 6 years 10 months ago. No further extension recordedExtended by 1 year (originally December 2018). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- All booked118 units booked
Project facts
| 1 BHK | 106 |
|---|---|
| 2 BHK | 12 |
| Total units | 118 |
| Buildings | 2 |
| Land | 1 acre |
| Complaints on MahaRERA (filed by or against the builder) | 2 |
Compared with 3 similar projects in PIN 412105
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 1 yr 4 mths | 5 yrs 5 mths |
| Possession date extended | By 1 year | 3 of 3 |
| Possession date passed | Yes, due December 2019 | 1 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 100% | 42% |
| Complaints on MahaRERA (filed by or against the builder) | 2 | 2 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Santiago Skymont | September 2017 | December 2030 | 33% | 59 of 142 booked (42%) |
| Tanishq Vlasta | July 2017 | December 2023 | 100% | 183 of 217 booked (84%) |
| Dnyanvishwa | January 2018 | December 2030 | 100% | 85 of 239 booked (36%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 118 | |
| 100% | 100% | 93% | 118 |
"—" means MahaRERA shows no figure for that update.
About this project
Suvarna Alay (MahaRERA P52100006825) is a residential project by Maheshwari Developers in Charholi Khurd, Pune 412105. It was launched in August 2017. It has 118 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in December 2019, after an extension of 1 year from the original December 2018. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
All 118 units are booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.