Santiago Skymont, Charholi
by Asha Heritage Developers. Charholi, Pune 412105. View on Google Maps
- Launched
- 3 years 3 months originally promised
- Possession date (MahaRERA)
- 4 years 2 months awayExtended by 10 years (originally December 2020). Why possession dates change
- Concrete structure (RCC)
- 33%Mid-constructionAverage across 3 buildings
- Units booked
- 59 of 14242% booked
Project facts
| 1 BHK | 70 |
|---|---|
| 2 BHK | 72 |
| Total units | 142 |
| Buildings | 3 |
| Land | 1.8 acres |
| Landowner share | 33 |
| Complaints on MahaRERA (filed by or against the builder) | 2 |
Compared with 4 similar projects in PIN 412105
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 3 mths | 4 yrs 4 mths |
| Possession date extended | By 10 years | 4 of 4 |
| Possession date (MahaRERA) | December 2030 | December 2030 |
| Concrete structure (RCC) complete | 33% | 100% |
| Share of units booked | 42% | 68% |
| Complaints on MahaRERA (filed by or against the builder) | 2 | 2 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Suvarna Alay | August 2017 | December 2019 | 100% | All 118 units booked |
| Dwarka Square Phase I | August 2017 | December 2023 | 60% | 139 of 262 booked (53%) |
| Tanishq Vlasta | July 2017 | December 2023 | 100% | 183 of 217 booked (84%) |
| Dnyanvishwa | January 2018 | December 2030 | 100% | 85 of 239 booked (36%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 33% | 33% | 32% | 59 | |
| 67% | 33% | 32% | 59 | |
| 67% | 33% | 3% | 39 |
"—" means MahaRERA shows no figure for that update.
About this project
Santiago Skymont (MahaRERA P52100012533) is a residential project by Asha Heritage Developers in Charholi, Pune 412105. It was launched in September 2017. It has 142 units in 3 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2030, extended by 10 years from the original December 2020. Construction, averaged across its 3 buildings: excavation 33% complete, structure (RCC) 33% complete, final finishes 32% complete. MahaRERA records do not show it as ready to move in.
59 of its 142 units are booked (42%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.