Laxmi Vishwa, Medankarwadi
by Tulsi Buildtech. Medankarwadi, Pune 410501. View on Google Maps
- Launched
- 7 years 4 months originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 2 years (originally December 2024). Why possession dates change
- Concrete structure (RCC)
- 50%Mid-constructionAverage across 4 buildings
- Units booked
- 54 of 17830% booked
Project facts
| 1 BHK | 80 |
|---|---|
| 2 BHK | 78 |
| Other units (shops, offices or not given by type) | 20 |
| Total units | 178 |
| Buildings | 4 |
| Land | 2.5 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: possession date December 2024 → December 2026
Compared with 6 similar projects in PIN 410501
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 7 yrs 4 mths | 2 yrs 4 mths |
| Possession date extended | By 2 years | 6 of 6 |
| Possession date (MahaRERA) | December 2026 | December 2030 |
| Concrete structure (RCC) complete | 50% | 100% |
| Share of units booked | 30% | 68% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 3 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Phase IV - K1 and L1 Buildings | August 2017 | December 2025 | 100% | All 176 units booked |
| The Urbana | August 2017 | March 2026 | 100% | 110 of 119 booked (92%) |
| Amrutvel | August 2017 | March 2025 | 100% | 58 of 125 booked (46%) |
| Urja Cornerstone Building 2 | August 2017 | December 2020 | 100% | 34 of 98 booked (35%) |
| Urban County A & B Wing | August 2017 | October 2023 | 100% | 86 of 95 booked (91%) |
| Phase I - Buildings A, A1, P and S,T,U Combined wing | August 2017 | December 2030 | 100% | 113 of 245 booked (46%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 50% | 46% | 54 | |
| 50% | 35% | 0% | 54 |
"—" means MahaRERA shows no figure for that update.
About this project
Laxmi Vishwa (MahaRERA P52100003933) is a residential project by Tulsi Buildtech in Medankarwadi, Pune 410501. It was launched in August 2017. It has 178 units in 4 buildings: 158 homes (1 & 2 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction, averaged across its 4 buildings: excavation 50% complete, structure (RCC) 50% complete, final finishes 46% complete. MahaRERA records do not show it as ready to move in.
54 of its 178 units are booked (30%). Since the December 2025 update, the possession date has moved from December 2024 to December 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.