Urban County A & B Wing, Nanekarwadi
by Padmalaya Properties. Nanekarwadi, Pune 410501. View on Google Maps
- Launched
- 3 years 10 months originally promised
- Possession date (MahaRERA)
- 3 years ago. No further extension recordedExtended by 2 years 4 months (originally June 2021). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 86 of 9591% booked
Project facts
| 1 BHK | 47 |
|---|---|
| 2 BHK | 47 |
| 3 BHK | 1 |
| Total units | 95 |
| Buildings | 1 |
| Land | 0.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Compared with 6 similar projects in PIN 410501
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 10 mths | 2 yrs 4 mths |
| Possession date extended | By 2 years 4 months | 6 of 6 |
| Possession date passed | Yes, due October 2023 | 2 ready to move; 3 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 91% | 69% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 3 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Urja Cornerstone Building 2 | August 2017 | December 2020 | 100% | 34 of 98 booked (35%) |
| Amrutvel | August 2017 | March 2025 | 100% | 58 of 125 booked (46%) |
| The Urbana | August 2017 | March 2026 | 100% | 110 of 119 booked (92%) |
| Laxmi Vishwa | August 2017 | December 2026 | 50% | 54 of 178 booked (30%) |
| Phase IV - K1 and L1 Buildings | August 2017 | December 2025 | 100% | All 176 units booked |
| Ivory Tathastu | July 2017 | December 2023 | 100% | 121 of 127 booked (95%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 75% | 86 | |
| 100% | 100% | 10% | 40 |
"—" means MahaRERA shows no figure for that update.
About this project
Urban County A & B Wing (MahaRERA P52100009754) is a residential project by Padmalaya Properties in Nanekarwadi, Pune 410501. It was launched in August 2017. It has 95 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in October 2023, after an extension of 2 years 4 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete. MahaRERA records do not show it as ready to move in.
86 of its 95 units are booked (91%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.