Chandrarang Serenity, Wakad

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Chandrarang Developer and Builders PVT. Ltd.. Wakad, Pune 411057. View on Google Maps

Launched
9 years promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stageAverage across 6 buildings
Units booked
170 of 32053% booked
Price per sq ft (incl. balconies and terrace)
₹11,7002026 so far · 11 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK63
2 BHK251
3 BHK4
Other units (shops, offices or not given by type)2
Total units320
Buildings6
Land2 acres
Landowner share148
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 26 → 170 · structure 50% → 100% · final finishes 50% → 100% · total units 127 → 320

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
820 sq ft₹86 – 96 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,200 per sq ft17 sales
2026 so far₹11,700 per sq ft11 sales

Rate vs other Wakad projects, 2026: about 5% higher

Compared with 3 similar projects in PIN 411057

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)9 yrs6 yrs 7 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)December 2028March 2027
Concrete structure (RCC) complete100%100%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
6 years 10 months of the promised 9 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 80%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 50%Jun 2024: Concrete structure (RCC) 50%Dec 2024: Concrete structure (RCC) 50%Jun 2025: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 18%Jun 2024: Final finishes 50%Dec 2024: Final finishes 50%Jun 2025: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%170
100%50%50%26
100%50%50%89
80%50%18%89

"—" means MahaRERA shows no figure for that update.

About this project

Chandrarang Serenity (MahaRERA P52100023540) is a residential project by Chandrarang Developer and Builders PVT. Ltd. in Wakad, Pune 411057. It was launched in December 2019. It has 320 units in 6 buildings: 318 homes (1, 2 & 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 6 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

170 of its 320 units are booked (53%). Since the December 2025 update, 144 more units have been booked and the reported concrete structure (RCC) has gone from 50% to 100%. 80% of the 2026 (so far) sales we found here were at ₹11,700 per sq ft or less, counting balconies and terrace in the size, based on 11 registered sales. Buyers here paid a rate about 5% higher than at other Wakad projects in 2026. Most buyers paid ₹86–96 lakh for flats of 820 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100023540.Check it on MahaRERA (P52100023540)All projects in Wakad, Hinjewadi, Marunji