Skip to main content
← Back

Park 59, Wakad

by Shiv Developers. Wakad, Pune 411057. View on Google Maps

Launched
6 years 7 months promised
Possession date (MahaRERA)
1 month agoPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 5 buildings
Units booked
144 of 23063% booked

Project facts

2 BHK162
3 BHK68
Total units230
Name as registered on MahaRERAPARK59
Buildings5
Land1.4 acres
Landowner share38
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 147 → 144 · structure 60% → 100% · final finishes 36% → 68% · total units 213 → 230

Share on WhatsApp

Compared with 5 similar projects in PIN 411057

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs 7 mths6 yrs 1 mth
Possession date extendedNo2 of 5
Possession date (MahaRERA)September 2026September 2027
Concrete structure (RCC) complete100%100%
Share of units booked63%76%
Complaints on MahaRERA (filed by or against the builder)01

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 6 years 7 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 80%Jun 2024: Excavation 80%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 80%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 75%Jun 2024: Concrete structure (RCC) 60%Dec 2024: Concrete structure (RCC) 75%Jun 2025: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 36%Dec 2024: Final finishes 45%Jun 2025: Final finishes 45%Dec 2025: Final finishes 36%Jul 2026: Final finishes 68%Excavation 100%Concrete structure (RCC) 100%Final finishes 68%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%68%144
80%60%36%147
100%75%45%147
80%60%36%166
80%75%0%87

"—" means MahaRERA shows no figure for that update.

About this project

Park 59 (MahaRERA P52100024649) is a residential project by Shiv Developers in Wakad, Pune 411057. It was launched in February 2020. It has 230 units in 5 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2026, unchanged since launch. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) complete, final finishes 68% complete. MahaRERA records do not show it as ready to move in.

144 of its 230 units are booked (63%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 60% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100024649.Check it on MahaRERA (P52100024649)All projects in Wakad, Hinjewadi, Marunji