Livmo Phase I, Bhoirwadi
Finishing stageLapsed
Final finishes 90% · completion not yet filed on MahaRERA
by Priyanka Builders. Bhoirwadi, Pune 411057. View on Google Maps
- Launched
- 3 years 9 months originally promised
- Possession date (MahaRERA)
- 1 year 10 months ago. No further extension recordedExtended by 1 year (originally December 2023). What "Lapsed" means
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 220 of 23494% booked
Project facts
| 1 BHK | 220 |
|---|---|
| Other units (shops, offices or not given by type) | 14 |
| Total units | 234 |
| Buildings | 1 |
| Land | 2.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 3 |
Since Dec 2025: final finishes 98% → 90%
Compared with 5 similar projects in PIN 411057
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 9 mths | 6 yrs 7 mths |
| Possession date extended | By 1 year | 1 of 5 |
| Possession date passed | Yes, due December 2024 | 2 ready to move; 1 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 94% | 62% |
| Complaints on MahaRERA (filed by or against the builder) | 3 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Park 59 | February 2020 | September 2026 | 100% | 144 of 230 booked (63%) |
| Ira | April 2020 | September 2027 | 0% | Bookings not reported |
| Chandrarang Serenity | December 2019 | December 2028 | 100% | 170 of 320 booked (53%) |
| The Legend Phase II | August 2020 | June 2026 | 33% | 149 of 244 booked (61%) |
| ANP Memento | August 2020 | September 2026 | 100% | 338 of 368 booked (92%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 220 | |
| 100% | 100% | 98% | 220 | |
| 100% | 100% | 20% | 220 | |
| 100% | 100% | 10% | 219 | |
| 100% | 80% | 0% | 212 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Livmo Phase I (MahaRERA P52100025084) is a residential project by Priyanka Builders in Bhoirwadi, Pune 411057. It was launched in March 2020. It has 234 units in 1 building: 220 homes (1 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
220 of its 234 units are booked (94%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.