Ganga Amber PH II, Tathawade
by Shri Siddhivinayak Developers. Tathawade, Pune 411033. View on Google Maps
- Launched
- 4 years 10 months originally promised
- Possession date (MahaRERA)
- 4 months ago. No further extension recordedExtended by 1 year (originally June 2025). Why possession dates change
- Concrete structure (RCC)
- 93%Mid-constructionAverage across 2 buildings
- Units booked
- 90 of 20644% booked
- Price per sq ft (incl. balconies and terrace)
- ₹9,5002026 so far · 25 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 206 |
|---|---|
| Total units | 206 |
| Buildings | 2 |
| Land | 1.3 acres |
| Landowner share | 25 |
| Complaints on MahaRERA (filed by or against the builder) | 12 |
Since Dec 2025: booked 54 → 90 · structure 0% → 93% · final finishes 0% → 20% · total units 208 → 206
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 610 – 650 sq ft | ₹50 – 62 lakh |
| 770 – 790 sq ft | ₹56 – 73 lakh |
Based on flats sold in 2026 so far.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2026 so far | ₹9,500 per sq ft | 25 sales |
|---|
Rate vs other Tathawade projects, 2026: about 5% lower
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 93% | 20% | 90 | |
| 55% | 0% | 0% | 54 |
"—" means MahaRERA shows no figure for that update.
About this project
Ganga Amber PH II (MahaRERA P52100026055) is a residential project by Shri Siddhivinayak Developers in Tathawade, Pune 411033. It was launched in August 2020. It has 206 units in 2 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in June 2026, after an extension of 1 year from the original June 2025. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 93% complete, final finishes 20% complete. MahaRERA records do not show it as ready to move in.
90 of its 206 units are booked (44%). Since the December 2025 update, 36 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 93%. 80% of the 2026 (so far) sales we found here were at ₹9,500 per sq ft or less, counting balconies and terrace in the size, based on 25 registered sales. Buyers here paid a rate about 5% lower than at other Tathawade projects in 2026. Most buyers paid ₹50–62 lakh for flats of 610–650 sq ft and ₹56–73 lakh for 770–790 sq ft.
Goel Ganga's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 61 |
|---|---|
| Completed without extending the possession date | 18 |
| Completed after an extension, or lapsed | 14 |
| Under construction | 29 |
| Possession date extended by the builder | 16 |
| Typical time from launch to 100% structure | 5 years 1 month |
| Complaints on MahaRERA, all Goel Ganga projects | 141 (27 of 61 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.