VTP Sierra, Sus
by Prasanna Developers. Sus, Pune 411021. View on Google Maps
- Launched
- First of 2 phases
- Possession dates (MahaRERA)
- Dec 2026 – Jun 2029varies by phase1 of 2 phases have an extended possession date. Reading a project's possession date
- Concrete structure (RCC)
- 87%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
- Units booked
- 481 of 51394% booked
- Price per sq ft
- ₹10,7002024 salesSee what buyers paid
Facts
Project facts
| 2 BHK | 404 |
|---|---|
| 3 BHK | 104 |
| Total units | 513 |
| Buildings | 3 |
| Land | 0.5 acres |
| Phases | 2 |
| MahaRERA complaints (filed by or against the builder) | 8 |
Since Dec 2025: booked 480 → 481
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 2 BHK | about 730 – 840 sq ft | ₹75 – 89 lakh | 2024 sales |
Price per sq ft, year by year
| 2024 | ₹10,700 per sq ft |
|---|
Registered sales across all 2 phases.
Compared with the typical Sus rate in 2024: about 5% higher
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Phases
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| VTP Sierra PHASE-2 Nearing possession | P52100029394 | 356 | 100% | 98% | |
| VTP Sierra Phase 3 Mid-construction | P52100076811 | 152 | 56% | 84% |
Show updates by phase
VTP Sierra PHASE-2 (P52100029394)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 59% | 354 | |
| 100% | 100% | 30% | 353 | |
| 100% | 78% | 5% | 353 | |
| 100% | 35% | 0% | 282 | |
| 100% | 6% | 0% | 217 |
"—" means MahaRERA shows no figure for that update.
VTP Sierra Phase 3 (P52100076811)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 56% | 13% | 127 | |
| 100% | 0% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
Other phases of this project
About this project
VTP Sierra is a project by Prasanna Developers in Sus, Pune 411021, registered with MahaRERA as 2 phases (P52100029394, P52100076811). The first phase was launched in May 2021. Together the phases have 513 units in 3 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.
The phases' registered possession dates run from December 2026 to June 2029; 1 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 87% complete and final finishes 45% complete. 1 of the 2 phases have their structure complete.
481 of the 513 units reported for sale are booked (94%). In 2024 registered sales, 80% of flats here sold at ₹10,700 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate about 5% higher than the typical Sus rate in 2024. Most buyers paid ₹75–89 lakh for 2 BHK flats of about 730–840 sq ft (2024 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
VTP's track record in Pune
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Projects registered with MahaRERA | 70 |
|---|---|
| Completed without extending the possession date | 26 |
| Completed after an extension | 3 |
| Lapsed | 10 |
| Under construction | 31 |
| Possession date extended on the builder's application | 10 |
| Typical time from launch to 100% structure | 4 years 11 months |
| MahaRERA complaints (filed by or against the builder), all VTP projects | 656 (60 of 70 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and July 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.