Skip to main content
← Back

Godrej Hill Retreat, Mahalunge

Finishing stage

Final finishes 95% · completion not yet filed on MahaRERA

by Mahalunge Township Developers Private Limited. Mahalunge, Pune 411045. View on Google Maps

Launched
4 years 6 months originally promised
Possession date (MahaRERA)
2 months awayExtended by 1 year (originally December 2025). Why possession dates change
Concrete structure (RCC)
100%Finishing stageAverage across 3 buildings
Units booked
769 of 771100% booked

Project facts

1 RK3
1 BHK30
2 BHK527
3 BHK184
4 BHK3
Other units (shops, offices or not given by type)24
Total units771
Buildings3
Land4.2 acres
Complaints on MahaRERA (filed by or against the builder)45

Since Dec 2025: final finishes 71% → 95% · complaints 2 → 45

Share on WhatsApp

Compared with 3 similar projects in PIN 411045

Projects with 350–1,500 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 6 mths5 yrs 2 mths
Possession date extendedBy 1 year1 of 3
Possession date (MahaRERA)December 2026December 2026
Concrete structure (RCC) complete100%100%
Share of units booked100%87%
Complaints on MahaRERA (filed by or against the builder)450

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 6 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 69%Jun 2024: Concrete structure (RCC) 97%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 16%Jun 2024: Final finishes 22%Dec 2024: Final finishes 41%Jun 2025: Final finishes 41%Dec 2025: Final finishes 71%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%769
100%100%71%769
100%100%41%742
100%97%22%742
100%69%16%726

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Godrej Hill Retreat (MahaRERA P52100029559) is a residential project by Mahalunge Township Developers Private Limited in Mahalunge, Pune 411045. It was launched in June 2021. It has 771 units in 3 buildings: 747 homes (1 RK, 1 BHK, 2 BHK, 3 BHK & 4 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

769 of its 771 units are booked (100%).

Godrej's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA41
Completed without extending the possession date9
Completed after an extension, or lapsed2
Under construction30
Possession date extended by the builder11
Typical time from launch to 100% structure3 years 4 months
Complaints on MahaRERA, all Godrej projects441 (35 of 41 projects)

See all Godrej projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100029559.Check it on MahaRERA (P52100029559)All projects in Baner, Balewadi, Mahalunge