Skip to main content
← Back

Kumar Prospera - A6, Hadapsar

Finishing stageLapsed

Final finishes 100% · completion not yet filed on MahaRERA

by Kumar Agro Products Pvt Ltd - Kumar Company (Now known as Kumar Construction and Properties Pvt Ltd) JV. Hadapsar, Pune 411028. View on Google Maps

Launched
3 years 11 months originally promised
Possession date (MahaRERA)
1 year 2 months ago. No further extension recordedExtended by 2 months (originally June 2025). What "Lapsed" means
Concrete structure (RCC)
100%Finishing stage
Units booked
All booked92 units booked

Project facts

2 BHK46
3 BHK46
Total units92
Buildings1
Land0.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: final finishes 57% → 100% · possession date June 2025 → August 2025

Share on WhatsApp

Compared with 5 similar projects in PIN 411028

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411028
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths4 yrs 1 mth
Possession date extendedBy 2 months2 of 5
Possession date passedYes, due August 20251 ready to move; 1 also past their date
Concrete structure (RCC) complete100%67%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 6%Jun 2024: Final finishes 6%Dec 2024: Final finishes 13%Jun 2025: Final finishes 13%Dec 2025: Final finishes 57%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%92
100%100%57%92
100%100%13%92
100%100%6%92

"—" means MahaRERA shows no figure for that update.

About this project

Kumar Prospera - A6 (MahaRERA P52100029906) is a residential project by Kumar Agro Products Pvt Ltd - Kumar Company (Now known as Kumar Construction and Properties Pvt Ltd) JV in Hadapsar, Pune 411028. It was launched in July 2021. It has 92 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in August 2025, after an extension of 2 months from the original June 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

All 92 units are booked. Since the December 2025 update, the possession date has moved from June 2025 to August 2025.

Kumar's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA82
Completed without extending the possession date42
Completed after an extension, or lapsed5
Under construction35
Possession date extended by the builder5
Typical time from launch to 100% structure2 years 6 months
Complaints on MahaRERA, all Kumar projects71 (8 of 82 projects)

See all Kumar projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100029906.Check it on MahaRERA (P52100029906)All projects in Hadapsar, Handewadi