Skip to main content
← Back

Dodke Palazzo, Kothrud

Finishing stageLapsed

Final finishes 100% · completion not yet filed on MahaRERA

by Dodke Landmarks. Kothrud, Pune 411038. View on Google Maps

Launched
3 years 2 months originally promised
Possession date (MahaRERA)
1 year 4 months ago. No further extension recordedExtended by 6 months (originally December 2024). What "Lapsed" means
Concrete structure (RCC)
100%Finishing stageAverage across 2 buildings
Units booked
104 of 13478% booked
Price per sq ft (incl. balconies and terrace)
₹12,8002025 · 12 salesup 5% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK48
3 BHK20
4 BHK21
Other units (shops, offices or not given by type)45
Total units134
Buildings2
Land0.7 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 99 → 104

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
780 – 790 sq ft₹88 – 95 lakh
870 – 900 sq ft₹91 lakh – ₹1.12 crore
1,290 – 1,530 sq ft₹1.48 – 1.83 crore

Based on flats sold in 2024.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹12,200 per sq ft38 sales
2025up 5% on 2024₹12,800 per sq ft12 sales

Rate vs other Kothrud projects, 2025: about 25% lower

Compared with 5 similar projects in PIN 411038

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411038
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 2 mths3 yrs 9 mths
Possession date extendedBy 6 months3 of 5
Possession date passedYes, due June 20252 ready to move; 2 also past their date
Concrete structure (RCC) complete100%95%
Share of units booked78%40%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 2 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 44%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 15%Dec 2024: Final finishes 60%Jun 2025: Final finishes 60%Dec 2025: Final finishes 100%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%104
100%100%100%99
100%100%60%72
100%100%15%—
100%44%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Dodke Palazzo (MahaRERA P52100031044) is a residential project by Dodke Landmarks in Kothrud, Pune 411038. It was launched in October 2021. It has 134 units in 2 buildings: 89 homes (2, 3 & 4 BHK) and 45 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 6 months from the original December 2024. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

104 of its 134 units are booked (78%). Since the December 2025 update, 5 more units have been booked. 80% of the 2025 sales we found here were at ₹12,800 per sq ft or less (up 5% on 2024), counting balconies and terrace in the size, based on 12 registered sales. Buyers here paid a rate about 25% lower than at other Kothrud projects in 2025. Most buyers paid ₹88–95 lakh for flats of 780–790 sq ft, ₹91 lakh–₹1.12 crore for 870–900 sq ft and ₹1.48–1.83 crore for 1,290–1,530 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100031044.Check it on MahaRERA (P52100031044)All projects in Kothrud