Skip to main content
← Back

VTP Verve, Sus

by Prasanna Developers. Sus, Pune 411021. View on Google Maps

Launched
4 years 8 months originally promised
Possession date (MahaRERA)
3 years 2 months awayExtended by 3 years 6 months (originally June 2026). Why possession dates change
Concrete structure (RCC)
8%Mid-constructionAverage across 6 buildings
Units booked
644 of 70192% booked
Price per sq ft (incl. balconies and terrace)
₹11,0002024 · 11 sales80% of the 2024 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK469
3 BHK232
Total units701
Buildings6
Land2.1 acres
Complaints on MahaRERA (filed by or against the builder)5

Since Dec 2025: booked 589 → 644 · complaints 1 → 5

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹11,000 per sq ft11 sales

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 8 months have passed
Concrete structure (RCC) 8% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 94%Jun 2024: Excavation 97%Dec 2024: Excavation 98%Jun 2025: Excavation 98%Dec 2025: Excavation 98%Jul 2026: Excavation 98%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 8%Jun 2025: Concrete structure (RCC) 8%Dec 2025: Concrete structure (RCC) 8%Jul 2026: Concrete structure (RCC) 8%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 98%Concrete structure (RCC) 8%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
98%8%0%644
98%8%0%589
97%0%0%265
94%0%0%174

"—" means MahaRERA shows no figure for that update.

About this project

VTP Verve (MahaRERA P52100031556) is a residential project by Prasanna Developers in Sus, Pune 411021. It was launched in October 2021. It has 701 units in 6 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, extended by 3 years 6 months from the original June 2026. Construction, averaged across its 6 buildings: excavation 98% complete, structure (RCC) 8% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

644 of its 701 units are booked (92%). Since the December 2025 update, 55 more units have been booked. 80% of the 2024 sales we found here were at ₹11,000 per sq ft or less, counting balconies and terrace in the size, based on 11 registered sales.

VTP's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA70
Completed without extending the possession date26
Completed after an extension, or lapsed13
Under construction31
Possession date extended by the builder10
Typical time from launch to 100% structure4 years 11 months
Complaints on MahaRERA, all VTP projects656 (60 of 70 projects)

See all VTP projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100031556.Check it on MahaRERA (P52100031556)All projects in Bavdhan, Pashan, Sus