Skip to main content
← Back

M J Opera, Wakad

Lapsed

by M/S Shivdan Constructions. Wakad, Pune 411057. View on Google Maps

Launched
3 years 9 months originally promised
Possession date (MahaRERA)
8 months ago. No further extension recordedExtended by 4 months (originally October 2025). What "Lapsed" means
Concrete structure (RCC)
100%Nearing possessionAverage across 4 buildings
Units booked
214 of 24886% booked

Project facts

1 BHK6
2 BHK150
3 BHK76
Other units (shops, offices or not given by type)16
Total units248
Buildings4
Land2.2 acres
Landowner share11
Complaints on MahaRERA (filed by or against the builder)5

Since Dec 2025: booked 212 → 214 · final finishes 70% → 73% · complaints 0 → 5

Share on WhatsApp

Compared with 6 similar projects in PIN 411057

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 9 mths4 yrs 4 mths
Possession date extendedBy 4 months2 of 6
Possession date passedYes, due February 20263 ready to move; 1 also past their date
Concrete structure (RCC) complete100%100%
Share of units booked86%86%
Complaints on MahaRERA (filed by or against the builder)52

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 9 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 63%Jun 2024: Excavation 63%Dec 2024: Excavation 75%Jun 2025: Excavation 75%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 13%Jun 2024: Concrete structure (RCC) 13%Dec 2024: Concrete structure (RCC) 58%Jun 2025: Concrete structure (RCC) 58%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 70%Jul 2026: Final finishes 73%Excavation 100%Concrete structure (RCC) 100%Final finishes 73%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%73%214
100%100%70%212
75%58%0%174
63%13%0%174
63%13%0%160

"—" means MahaRERA shows no figure for that update.

About this project

M J Opera (MahaRERA P52100032413) is a residential project by M/S Shivdan Constructions in Wakad, Pune 411057. It was launched in January 2022. It has 248 units in 4 buildings: 232 homes (1, 2 & 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in February 2026, after an extension of 4 months from the original October 2025. That date has passed and no further extension has been recorded. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) complete, final finishes 73% complete. MahaRERA records do not show it as ready to move in.

214 of its 248 units are booked (86%). Since the December 2025 update, 2 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100032413.Check it on MahaRERA (P52100032413)All projects in Wakad, Hinjewadi, Marunji