Skip to main content
← Back

Life Republic Sector R16- 16th Avenue- Arezo- M Building, Jambhe

Finishing stageLapsed

Final finishes 100% · completion not yet filed on MahaRERA

by Kolte-Patil Integrated Townships Limited. Jambhe, Pune 411057. View on Google Maps

Launched
3 years 11 months promised
Possession date (MahaRERA)
1 year ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Finishing stage
Units booked
172 of 17399% booked

Project facts

2 BHK173
Total units173
Buildings1
Land0.6 acres
Complaints on MahaRERA (filed by or against the builder)34

Since Dec 2025: final finishes 85% → 100% · complaints 16 → 34

Share on WhatsApp

Compared with 6 similar projects in PIN 411057

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths3 yrs 8 mths
Possession date extendedNo5 of 6
Possession date passedYes, due October 20253 ready to move; 2 also past their date
Concrete structure (RCC) complete100%100%
Share of units booked99%82%
Complaints on MahaRERA (filed by or against the builder)340

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 3 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 40%Jun 2024: Concrete structure (RCC) 82%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 85%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%172
100%100%85%172
100%100%0%130
100%82%0%130
100%40%0%130

"—" means MahaRERA shows no figure for that update.

About this project

Life Republic Sector R16- 16th Avenue- Arezo- M Building (MahaRERA P52100031799) is a residential project by Kolte-Patil Integrated Townships Limited in Jambhe, Pune 411057. It was launched in November 2021. It has 173 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in October 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

172 of its 173 units are booked (99%).

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension, or lapsed17
Under construction35
Possession date extended by the builder4
Typical time from launch to 100% structure3 years
Complaints on MahaRERA, all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100031799.Check it on MahaRERA (P52100031799)All projects in Wakad, Hinjewadi, Marunji