ZEN Elite, Kharadi

Finishing stage

Final finishes 95% · completion not yet filed on MahaRERA

by Rion Buildtech Private Limited. Kharadi, Pune 411014. View on Google Maps

Launched
4 years 10 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stageAverage across 4 buildings
Units booked
391 of 44688% booked
Price per sq ft (incl. balconies and terrace)
₹10,8002024 · 18 sales80% of the 2024 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK44
2 BHK172
3 BHK230
Total units446
Buildings4
Land2.5 acres
Complaints on MahaRERA (filed by or against the builder)3

Since Dec 2025: booked 386 → 391 · final finishes 48% → 95%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
890 – 940 sq ft₹80 – 98 lakh

Based on flats sold in 2024.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,800 per sq ft18 sales

Studios (under 450 sq ft)

80% of the 2026 studio sales we found were at this rate or less

2026 so far₹4,300 per sq ft26 sales

Sizes 360 – 400 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Compared with 3 similar projects in PIN 411014

Projects with 200–900 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411014
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 10 mths5 yrs 7 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)December 2026December 2027
Concrete structure (RCC) complete100%100%
Share of units booked88%89%
Complaints on MahaRERA (filed by or against the builder)31

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 8 months of the promised 4 years 10 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 1%Jun 2024: Concrete structure (RCC) 1%Dec 2024: Concrete structure (RCC) 1%Jun 2025: Concrete structure (RCC) 1%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 48%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%391
100%100%48%386
100%1%0%398
100%1%0%—

"—" means MahaRERA shows no figure for that update.

About this project

ZEN Elite (MahaRERA P52100033357) is a residential project by Rion Buildtech Private Limited in Kharadi, Pune 411014. It was launched in February 2022. It has 446 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

391 of its 446 units are booked (88%). Since the December 2025 update, 5 more units have been booked. 80% of the 2024 sales we found here were at ₹10,800 per sq ft or less, counting balconies and terrace in the size, based on 18 registered sales. Most buyers paid ₹80–98 lakh for flats of 890–940 sq ft. Its studios (under 450 sq ft) sold at ₹4,300 per sq ft or less in 2026 (26 sales); studios are priced separately from flats.

Kohinoor's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA48
Completed without extending the possession date13
Completed after an extension, or lapsed10
Under construction25
Possession date extended by the builder8
Typical time from launch to 100% structure3 years 3 months
Complaints on MahaRERA, all Kohinoor projects52 (19 of 48 projects)

See all Kohinoor projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100033357.Check it on MahaRERA (P52100033357)All projects in Kharadi, Vadgaon Sheri, Viman Nagar