Surya Skies, Punawale
Finishing stageLapsed
Final finishes 95% · completion not yet filed on MahaRERA
by Surya Developer. Punawale, Pune 411033. View on Google Maps
- Launched
- 3 years 8 months originally promised
- Possession date (MahaRERA)
- 4 months ago. No further extension recordedExtended by 6 months (originally December 2025). What "Lapsed" means
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 202 of 20499% booked
Project facts
| 2 BHK | 152 |
|---|---|
| 3 BHK | 52 |
| Total units | 204 |
| Buildings | 2 |
| Land | 2.5 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 200 → 202 · final finishes 75% → 95% · possession date December 2025 → June 2026
Compared with 6 similar projects in PIN 411033
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 8 mths | 4 yrs 2 mths |
| Possession date extended | By 6 months | 2 of 6 |
| Possession date passed | Yes, due June 2026 | 2 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 79% |
| Share of units booked | 99% | 89% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vma Reserve | March 2022 | February 2026 | 100% | 133 of 154 booked (86%) |
| Mahindra Happinest Tathawade Phase 2 | May 2022 | May 2027 | 0% | 282 of 306 booked (92%) |
| 41 Cosmo | May 2022 | May 2027 | 100% | 262 of 266 booked (98%) |
| Harivishva Infinia Phase 1 | June 2022 | December 2026 | 100% | 199 of 207 booked (96%) |
| Sonigara the Mark Phase I | February 2022 | December 2028 | 58% | 134 of 234 booked (57%) |
| 12th Avenue | February 2022 | December 2028 | 50% | 128 of 171 booked (75%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 202 | |
| 100% | 100% | 75% | 200 | |
| 100% | 83% | 10% | 199 | |
| 100% | 10% | 0% | 197 |
"—" means MahaRERA shows no figure for that update.
About this project
Surya Skies (MahaRERA P52100034618) is a residential project by Surya Developer in Punawale, Pune 411033. It was launched in April 2022. It has 204 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 6 months from the original December 2025. That date has passed and no further extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
202 of its 204 units are booked (99%). Since the December 2025 update, 2 more units have been booked and the possession date has moved from December 2025 to June 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.