Park Astra, Marunji
by Pride Purple Infrastructure. Marunji, Pune 411057. View on Google Maps
- Launched
- First of 2 phases
- Possession dates (MahaRERA)
- Dec 2026No phase has an extended possession date
- Concrete structure (RCC)
- 100%Nearing possession2 of 2 phases with structure completeWeighted across 2 phases
- Units booked
- 233 of 26588% booked
- Price per sq ft
- ₹9,9002024 salesup 5% on 2023See what buyers paid
Facts
Project facts
| 2 BHK | 129 |
|---|---|
| 3 BHK | 136 |
| Total units | 265 |
| Buildings | 4 |
| Land | 1.3 acres |
| Phases | 2 |
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 2 BHK | about 690 – 890 sq ft | ₹70 – 84 lakh | 2024 sales |
Price per sq ft, year by year
| 2023 | ₹9,400 per sq ft |
|---|---|
| 2024up 5% on 2023 | ₹9,900 per sq ft |
Registered sales across all 2 phases.
Compared with the typical Marunji rate in 2024: similar
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Phases
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Park Astra Phase II Nearing possession | P52100045496 | 136 | 100% | 93% | |
| Park Astra Phase III Completed | P52100049640 | 129 | 100% | 82% |
Show updates by phase
Park Astra Phase II (P52100045496)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 127 | |
| 100% | 12% | 0% | 127 | |
| 100% | 12% | 0% | 73 |
"—" means MahaRERA shows no figure for that update.
Park Astra Phase III (P52100049640)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 106 | |
| 100% | 6% | 0% | 92 | |
| 100% | 6% | 0% | 13 |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 6 similar projects in PIN 411057
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs | 4 yrs 2 mths |
| Possession date extended | No | 3 of 6 |
| Possession date (MahaRERA) | Dec 2026 | January 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 88% | 87% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kuber Antonia | May 2022 | Feb 2026 – Apr 2027 | 89% | 121 of 152 booked (80%) |
| The Camelia Phase - 1 | May 2022 | January 2027 | 100% | 306 of 426 booked (72%) |
| TOP Towers | April 2022 | Jun 2026 – Jul 2027 | 50% | 132 of 309 booked (43%) |
| My Home Wakad | June 2022 | June 2027 | 100% | 203 of 207 booked (98%) |
| La Centra | April 2022 | Dec 2026 | 100% | 193 of 195 booked (99%) |
| RGS Forte | April 2022 | March 2027 | 100% | 176 of 185 booked (95%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
Other phases of this project
About this project
Park Astra is a project by Pride Purple Infrastructure in Marunji, Pune 411057, registered with MahaRERA as 2 phases (P52100045496, P52100049640). The first phase was launched in May 2022. Together the phases have 265 units in 4 buildings, with 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is active and 1 is completed.
The registered possession date is December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 0% complete. 2 of the 2 phases have their structure complete.
233 of the 265 units reported for sale are booked (88%). In 2024 registered sales, 80% of flats here sold at ₹9,900 per sq ft or less (up 5% on 2023), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Marunji rate in 2024. Most buyers paid ₹70–84 lakh for 2 BHK flats of about 690–890 sq ft (2024 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
Pride's track record in Pune
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Projects registered with MahaRERA | 27 |
|---|---|
| Completed without extending the possession date | 8 |
| Completed after an extension | 0 |
| Lapsed | 8 |
| Under construction | 11 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 2 years 7 months |
| MahaRERA complaints (filed by or against the builder), all Pride projects | 12 (11 of 27 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and July 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.