Wellington, Charholi

by Pride Builders LLP. Charholi, Pune 412105. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Sep 2026 – Dec 2027varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
100%Nearing possession4 of 4 phases with structure completeWeighted across 4 phases
Units booked
1,307 of 1,33898% booked
Price per sq ft
₹9,8002026 salesup 4% on 2025See what buyers paid

Project facts

2 BHK418
3 BHK890
4 BHK30
Total units1,338
Buildings10
Land2.2 acres
Phases4

Since Dec 2025: booked 1,271 → 1,307

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 780 sq ft₹67 – 74 lakh2025 sales
3 BHKabout 1,060 – 1,160 sq ft₹1.01 – 1.14 crore2026 sales
4 BHKabout 1,460 sq ft₹1.18 – 1.30 crore2024 sales

Price per sq ft, year by year

2023₹7,900 per sq ft
2024up 14% on 2023₹9,000 per sq ft
2025up 4% on 2024₹9,400 per sq ft
2026up 4% on 2025₹9,800 per sq ft

Registered sales across all 4 phases.

Compared with the typical Charholi rate in 2026: similar

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Wellington-l-m
Ready to move
P52100045786264100%98%
Wellington C - D
Ready to move
P52100048477264100%98%
Wellington-e-h-j-k
Nearing possession
P52100052379540100%97%
Wellington F-G
Nearing possession
P52100054534270100%99%
Show updates by phase

Wellington-l-m (P52100045786)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%258
100%100%50%256
100%100%20%252
100%76%0%245
100%32%0%245

"—" means MahaRERA shows no figure for that update.

Wellington C - D (P52100048477)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%259
100%100%100%255
100%100%25%207
100%80%0%201
100%28%0%201

"—" means MahaRERA shows no figure for that update.

Wellington-e-h-j-k (P52100052379)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%48%523
100%81%5%502
100%56%0%408
100%17%0%97
50%0%0%97

"—" means MahaRERA shows no figure for that update.

Wellington F-G (P52100054534)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%267
100%98%0%258
100%44%0%175
100%6%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 3 similar projects in PIN 412105

Projects with 600–2,700 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 1 mth4 yrs 11 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Sep 2026 – Dec 2027January 2028
Concrete structure (RCC)100%90%
Units booked98%88%
MahaRERA complaints (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Wellington is a project by Pride Builders LLP in Charholi, Pune 412105, registered with MahaRERA as 4 phases (P52100045786, P52100048477, P52100052379, P52100054534). The first phase was launched in June 2022. Together the phases have 1,338 units in 10 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.

The phases' registered possession dates run from September 2026 to December 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 59% complete. 4 of the 4 phases have their structure complete.

1,307 of the 1,338 units reported for sale are booked (98%). In 2026 registered sales, 80% of flats here sold at ₹9,800 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Charholi rate in 2026. Most buyers paid ₹67–74 lakh for 2 BHK flats of about 780 sq ft (2025 sales); ₹1.01–1.14 crore for 3 BHK flats of about 1,060–1,160 sq ft (2026 sales); ₹1.18–1.30 crore for 4 BHK flats of about 1,460 sq ft (2024 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Pride's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA27
Completed without extending the possession date8
Completed after an extension0
Lapsed8
Under construction11
Possession date extended on the builder's application0
Typical time from launch to 100% structure2 years 7 months
MahaRERA complaints (filed by or against the builder), all Pride projects12 (11 of 27 projects)

See all Pride projects →

Source: MahaRERA registrations P52100045786, P52100048477, P52100052379 and P52100054534.Open MahaRERA and search P52100045786All projects in Charholi, Moshi