Skip to main content
← Back

Pebbles Greenfields, Tathawade

by Abhinav Realty and Infrastructure LLP. Tathawade, Pune 411033. View on Google Maps

Launched
5 years promised
Possession date (MahaRERA)
8 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 4 buildings
Units booked
658 of 69495% booked
Price per sq ft (incl. balconies and terrace)
₹10,9002026 so far · 16 salesdown 3% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK349
3 BHK341
Other units (shops, offices or not given by type)4
Total units694
Buildings4
Land3.7 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 633 → 658 · structure 71% → 100% · final finishes 0% → 65%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,040 sq ft₹1.10 – 1.13 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,700 per sq ft74 sales
2025up 5% on 2024₹11,200 per sq ft34 sales
2026 so fardown 3% on 2025₹10,900 per sq ft16 sales

Rate vs other Tathawade projects, 2026: about 10% higher

Compared with 6 similar projects in PIN 411033

Projects with 300–1,400 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs5 yrs 6 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)June 2027December 2028
Concrete structure (RCC) complete100%80%
Share of units booked95%70%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 4 months of the promised 5 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 99%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 2%Jun 2024: Concrete structure (RCC) 40%Dec 2024: Concrete structure (RCC) 40%Jun 2025: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 71%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 65%Excavation 100%Concrete structure (RCC) 100%Final finishes 65%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%65%658
100%71%0%633
100%40%0%530
99%2%0%438

"—" means MahaRERA shows no figure for that update.

About this project

Pebbles Greenfields (MahaRERA P52100045923) is a residential project by Abhinav Realty and Infrastructure LLP in Tathawade, Pune 411033. It was launched in June 2022. It has 694 units in 4 buildings: 690 homes (2 & 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) complete, final finishes 65% complete. MahaRERA records do not show it as ready to move in.

658 of its 694 units are booked (95%). Since the December 2025 update, 25 more units have been booked and the reported concrete structure (RCC) has gone from 71% to 100%. 80% of the 2026 (so far) sales we found here were at ₹10,900 per sq ft or less (down 3% on 2025), counting balconies and terrace in the size, based on 16 registered sales. Buyers here paid a rate about 10% higher than at other Tathawade projects in 2026. Most buyers paid ₹1.10–1.13 crore for flats of 1,040 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100045923.Check it on MahaRERA (P52100045923)All projects in Tathawade, Punawale, Jambhe