YashONE Eternitee, Maan
by Vilas Javdekar Infinitee Developers Pvt. Ltd.. Maan, Pune 411057. View on Google Maps
- Launched
- First of 2 phases
- Possession dates (MahaRERA)
- Jun 2027No phase has an extended possession date
- Concrete structure (RCC)
- 74%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
- Units booked
- 1,021 of 1,021100% booked
- Price per sq ft
- ₹8,9002024 salesup 2% on 2023See what buyers paid
Facts
Project facts
| 1 BHK | 126 |
|---|---|
| 2 BHK | 457 |
| 3 BHK | 418 |
| Total units | 1,021 |
| Buildings | 7 |
| Land | 5 acres |
| Phases | 2 |
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 1 RK / 1 BHK | about 480 sq ft | ₹42 – 44 lakh | 2024 sales |
| 2 BHK | about 700 – 870 sq ft | ₹60 – 76 lakh | 2024 sales |
| 3 BHK | about 990 sq ft | ₹83 – 85 lakh | 2024 sales |
Price per sq ft, year by year
| 2023 | ₹8,700 per sq ft |
|---|---|
| 2024up 2% on 2023 | ₹8,900 per sq ft |
Registered sales across all 2 phases.
Compared with the typical Maan rate in 2024: about 10% lower
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Phases
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| YashONE Eternitee Phase 1 Completed | P52100046122 | 382 | 100% | 100% | |
| Yashone Eternitee Phase 2 Mid-construction | P52100052676 | 619 | 58% | 100% |
Show updates by phase
YashONE Eternitee Phase 1 (P52100046122)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 65% | 382 | |
| 100% | 100% | 25% | 381 | |
| 100% | 100% | 0% | 382 | |
| 100% | 58% | 0% | 380 |
"—" means MahaRERA shows no figure for that update.
Yashone Eternitee Phase 2 (P52100052676)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 58% | 0% | 639 | |
| 100% | 50% | 0% | 639 | |
| 80% | 7% | 0% | 678 | |
| 67% | 2% | 0% | 635 | |
| 37% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 5 similar projects in PIN 411057
Projects with 500–2,100 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 10 mths | 4 yrs 2 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | Jun 2027 | December 2026 |
| Concrete structure (RCC) | 74% | 83% |
| Units booked | 100% | 91% |
| MahaRERA complaints (filed by or against the builder) | 1 | 1 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Godrej Woodsville | September 2022 | November 2026 | 100% | 986 of 992 booked (99%) |
| VTP Bellissimo | March 2022 | Dec 2026 – Dec 2027 | 77% | 1,469 of 1,610 booked (91%) |
| ANP Ultimus | November 2022 | June 2027 | 83% | 645 of 840 booked (77%) |
| Life Republic Sector R13/13th Avenue/Aros Phase I | December 2022 | December 2026 | 100% | 689 of 739 booked (93%) |
| Park Titan | November 2021 | Jun 2026 – Aug 2029 | 54% | 1,010 of 1,199 booked (84%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
YashONE Eternitee is a project by Vilas Javdekar Infinitee Developers Pvt. Ltd. in Maan, Pune 411057, registered with MahaRERA as 2 phases (P52100046122, P52100052676). The first phase was launched in June 2022. Together the phases have 1,021 units in 7 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.
The registered possession date is June 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 74% complete and final finishes 25% complete. 1 of the 2 phases have their structure complete.
1,021 of the 1,021 units reported for sale are booked (100%). In 2024 registered sales, 80% of flats here sold at ₹8,900 per sq ft or less (up 2% on 2023), counting balconies and terrace in the size. Buyers here paid a rate about 10% lower than the typical Maan rate in 2024. Most buyers paid ₹42–44 lakh for 1 RK / 1 BHK flats of about 480 sq ft (2024 sales); ₹60–76 lakh for 2 BHK flats of about 700–870 sq ft (2024 sales); ₹83–85 lakh for 3 BHK flats of about 990 sq ft (2024 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.