VTP Bellissimo, Hinjewadi

by Magnite Developers Private Limited. Hinjewadi, Pune 411057. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Dec 2026 – Dec 2027varies by phase2 of 3 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
77%Mid-construction0 of 3 phases with structure completeWeighted across 3 phases
Units booked
1,469 of 1,61091% booked
Price per sq ft
₹11,6002026 salesSee what buyers paid

Project facts

1 BHK205
2 BHK978
3 BHK407
Total units1,610
Buildings9
Land1.1 acres
Phases3

Since Dec 2025: booked 1,449 → 1,469

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
1 RK / 1 BHKabout 470 sq ft₹43 – 45 lakh2023 sales
2 BHKabout 620 – 770 sq ft₹74 – 91 lakh2026 sales
3 BHKabout 910 – 1,220 sq ft₹1.00 – 1.26 crore2023 sales

Price per sq ft, year by year

2023₹10,000 per sq ft
2024up 5% on 2023₹10,500 per sq ft
2026₹11,600 per sq ft

Registered sales across all 3 phases.

Compared with the typical Hinjewadi rate in 2026: about 5% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
VTP Bellissimo Phase 1
Mid-construction
P521000338881,22685%96%
VTP Bellissimo Phase 2
Mid-construction
P5210004724615672%87%
VTP Bellissimo Phase 3
Mid-construction
P5210004833120835%69%
Show updates by phase

VTP Bellissimo Phase 1 (P52100033888)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%1,191
100%29%0%1,178
100%29%0%1,193
100%20%0%1,193
100%3%0%451

"—" means MahaRERA shows no figure for that update.

VTP Bellissimo Phase 2 (P52100047246)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%0%135
100%8%0%133
100%0%0%131
100%0%0%127

"—" means MahaRERA shows no figure for that update.

VTP Bellissimo Phase 3 (P52100048331)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%0%143
100%0%0%138
100%0%0%135
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 3 similar projects in PIN 411057

Projects with 700–3,200 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 2 mths4 yrs 2 mths
Possession date extendedYes0 of 3
Possession date (MahaRERA)Dec 2026 – Dec 2027November 2026
Concrete structure (RCC)77%74%
Units booked91%99%
MahaRERA complaints (filed by or against the builder)141

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

VTP Bellissimo is a project by Magnite Developers Private Limited in Hinjewadi, Pune 411057, registered with MahaRERA as 3 phases (P52100033888, P52100047246, P52100048331). The first phase was launched in March 2022. Together the phases have 1,610 units in 9 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from December 2026 to December 2027; 2 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 77% complete and final finishes 0% complete. 0 of the 3 phases have their structure complete.

1,469 of the 1,610 units reported for sale are booked (91%). In 2026 registered sales, 80% of flats here sold at ₹11,600 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Hinjewadi rate in 2026. Most buyers paid ₹43–45 lakh for 1 RK / 1 BHK flats of about 470 sq ft (2023 sales); ₹74–91 lakh for 2 BHK flats of about 620–770 sq ft (2026 sales); ₹1.00–1.26 crore for 3 BHK flats of about 910–1,220 sq ft (2023 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

VTP's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA70
Completed without extending the possession date26
Completed after an extension3
Lapsed10
Under construction31
Possession date extended on the builder's application10
Typical time from launch to 100% structure4 years 11 months
MahaRERA complaints (filed by or against the builder), all VTP projects656 (60 of 70 projects)

See all VTP projects →

Source: MahaRERA registrations P52100033888, P52100047246 and P52100048331.Open MahaRERA and search P52100033888All projects in Wakad, Hinjewadi, Marunji