Skip to main content
← Back

Life Republic Sector R13/13th Avenue/Aros/Phase I, Nere

by Kolte-Patil Developers Limited. Nere, Pune 411057. View on Google Maps

Launched
4 years promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 5 buildings
Units booked
689 of 73993% booked

Project facts

2 BHK320
3 BHK368
Other units (shops, offices or not given by type)51
Total units739
Buildings5
Land2.3 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 681 → 689 · final finishes 0% → 76%

Share on WhatsApp

Compared with 4 similar projects in PIN 411057

Projects with 300–1,400 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs4 yrs 3 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)December 2026March 2027
Concrete structure (RCC) complete100%84%
Share of units booked93%92%
Complaints on MahaRERA (filed by or against the builder)02

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 10 months of the promised 4 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 13%Jun 2024: Concrete structure (RCC) 69%Dec 2024: Concrete structure (RCC) 94%Jun 2025: Concrete structure (RCC) 94%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 76%Excavation 100%Concrete structure (RCC) 100%Final finishes 76%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%76%689
100%100%0%681
100%94%0%411
100%69%0%411
100%13%0%411

"—" means MahaRERA shows no figure for that update.

About this project

Life Republic Sector R13/13th Avenue/Aros/Phase I (MahaRERA P52100047921) is a residential project by Kolte-Patil Developers Limited in Nere, Pune 411057. It was launched in December 2022. It has 739 units in 5 buildings: 688 homes (2 & 3 BHK) and 51 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) complete, final finishes 76% complete. MahaRERA records do not show it as ready to move in.

689 of its 739 units are booked (93%). Since the December 2025 update, 8 more units have been booked.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension, or lapsed17
Under construction35
Possession date extended by the builder4
Typical time from launch to 100% structure3 years
Complaints on MahaRERA, all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100047921.Check it on MahaRERA (P52100047921)All projects in Wakad, Hinjewadi, Marunji