Alpine Astonia, Kiwale
Finishing stageLapsed
Final finishes 100% · completion not yet filed on MahaRERA
by Alpine Landmarks LLP. Kiwale, Pune 412101. View on Google Maps
- Launched
- 3 years 5 months promised
- Possession date (MahaRERA)
- 6 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 160 of 23668% booked
Project facts
| 2 BHK | 85 |
|---|---|
| 3 BHK | 87 |
| Other units (shops, offices or not given by type) | 64 |
| Total units | 236 |
| Buildings | 2 |
| Land | 1 acre |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 157 → 160 · final finishes 65% → 100%
Compared with 6 similar projects in PIN 412101
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 5 mths | 3 yrs 8 mths |
| Possession date extended | No | 2 of 6 |
| Possession date passed | Yes, due April 2026 | 3 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 98% |
| Share of units booked | 68% | 70% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Little Earth, Kiwale- Building B11 | November 2022 | December 2026 | 100% | 24 of 172 booked (14%) |
| Little Earth, Kiwale Building C16 | November 2022 | June 2025 | 100% | 112 of 115 booked (97%) |
| City One Vezdaa | November 2022 | December 2028 | 90% | 264 of 367 booked (72%) |
| Solasta A Building | October 2022 | December 2026 | 100% | 107 of 157 booked (68%) |
| Terra Greens | December 2022 | December 2026 | 95% | 93 of 180 booked (52%) |
| Astoria Royals A wing | December 2022 | September 2028 | 50% | 108 of 144 booked (75%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 160 | |
| 100% | 100% | 65% | 157 | |
| 100% | 98% | 0% | 137 | |
| 100% | 47% | 0% | 108 | |
| 100% | 41% | 0% | 65 |
"—" means MahaRERA shows no figure for that update.
About this project
Alpine Astonia (MahaRERA P52100047595) is a residential project by Alpine Landmarks LLP in Kiwale, Pune 412101. It was launched in November 2022. It has 236 units in 2 buildings: 172 homes (2 & 3 BHK) and 64 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in April 2026. That date has passed and no extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
160 of its 236 units are booked (68%). Since the December 2025 update, 3 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.