Skip to main content
← Back

Kumar Purab A3 Building, Hadapsar

by Kumar & Potnis Associates. Hadapsar, Pune 411028. View on Google Maps

Launched
5 years 1 month promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possession
Units booked
118 of 13488% booked

Project facts

2 BHK112
3 BHK16
Other units (shops, offices or not given by type)6
Total units134
Buildings1
Land0.3 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 95 → 118 · final finishes 0% → 6%

Share on WhatsApp

Compared with 5 similar projects in PIN 411028

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411028
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 1 mth3 yrs 3 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)December 2027December 2026
Concrete structure (RCC) complete100%100%
Share of units booked88%81%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 11 months of the promised 5 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 48%Dec 2024: Concrete structure (RCC) 77%Jun 2025: Concrete structure (RCC) 77%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 6%Excavation 100%Concrete structure (RCC) 100%Final finishes 6%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%6%118
100%100%0%95
100%77%0%61
100%48%0%43
100%0%0%31

"—" means MahaRERA shows no figure for that update.

About this project

Kumar Purab A3 Building (MahaRERA P52100047614) is a residential project by Kumar & Potnis Associates in Hadapsar, Pune 411028. It was launched in November 2022. It has 134 units in 1 building: 128 homes (2 & 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 6% complete. MahaRERA records do not show it as ready to move in.

118 of its 134 units are booked (88%). Since the December 2025 update, 23 more units have been booked.

Kumar's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA82
Completed without extending the possession date42
Completed after an extension, or lapsed5
Under construction35
Possession date extended by the builder5
Typical time from launch to 100% structure2 years 6 months
Complaints on MahaRERA, all Kumar projects71 (8 of 82 projects)

See all Kumar projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100047614.Check it on MahaRERA (P52100047614)All projects in Hadapsar, Handewadi