- Launched
- 2 years 11 months originally promised
- Possession date (MahaRERA)
- 4 months ago. No further extension recordedExtended by 6 months (originally December 2025). What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 73 of 13056% booked
Project facts
| 2 BHK | 130 |
|---|---|
| Total units | 130 |
| Buildings | 1 |
| Land | 1.1 acres |
| Landowner share | 30 |
| Reserved units | 2 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 61 → 73 · final finishes 15% → 50% · possession date December 2025 → June 2026
Compared with 6 similar projects in PIN 411028
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 11 mths | 4 yrs |
| Possession date extended | By 6 months | 0 of 6 |
| Possession date passed | Yes, due June 2026 | 0 ready to move; 2 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 56% | 89% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The High Gates | January 2023 | December 2026 | 97% | 161 of 271 booked (59%) |
| Kumar Parc Residences - C MHADA | December 2022 | November 2025 | 100% | 114 of 140 booked (81%) |
| Kumar Purab A3 Building | November 2022 | December 2027 | 100% | 118 of 134 booked (88%) |
| Paradise - B2 and B3 | March 2023 | June 2026 | 100% | 79 of 88 booked (90%) |
| Kumar Parc Residences - B2 | March 2023 | December 2027 | 99% | 221 of 230 booked (96%) |
| Amanora Crown Towers | October 2022 | December 2026 | 100% | 286 of 292 booked (98%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 73 | |
| 100% | 100% | 15% | 61 | |
| 100% | 50% | 0% | 28 | |
| 100% | 80% | 0% | 20 | |
| 100% | 0% | 0% | 7 |
"—" means MahaRERA shows no figure for that update.
About this project
Sky Crest (MahaRERA P52100048382) is a residential project by Rahul Properties in Hadapsar, Pune 411028. It was launched in January 2023. It has 130 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 6 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
73 of its 130 units are booked (56%). Since the December 2025 update, 12 more units have been booked and the possession date has moved from December 2025 to June 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.