SkyHigh Towers, Maan

by New World Landmark LLP. Maan, Pune 411057. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2027 – Dec 2029varies by phase1 of 2 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
34%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
89 of 13665% booked · 1 phase not reported
Price per sq ft
₹9,2002026 salesSee what buyers paid

Project facts

1 RK13
1 BHK4
2 BHK279
Total units296
Buildings2
Land8.4 acres
Phases2

Since Dec 2025: booked 84 → 89

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 660 – 850 sq ft₹61 – 67 lakh2026 sales

Price per sq ft, year by year

2026₹9,200 per sq ft

Registered sales across all 2 phases.

Compared with the typical Maan rate in 2026: about 15% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
SkyHigh Towers D4
Early stage
P521000484031530%Not reported
SkyHigh Towers D3
Mid-construction
P5210004841313075%65%
Show updates by phase

SkyHigh Towers D4 (P52100048403)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%—

"—" means MahaRERA shows no figure for that update.

SkyHigh Towers D3 (P52100048413)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%0%89
100%65%0%84
100%56%0%6
100%17%0%6

"—" means MahaRERA shows no figure for that update.

Compared with 4 similar projects in PIN 411057

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 5 mths4 yrs 6 mths
Possession date extendedYes0 of 4
Possession date (MahaRERA)Dec 2027 – Dec 2029January 2028
Concrete structure (RCC)34%82%
Units booked65%84%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

SkyHigh Towers is a project by New World Landmark LLP in Maan, Pune 411057, registered with MahaRERA as 2 phases (P52100048403, P52100048413). The first phase was launched in January 2023. Together the phases have 296 units in 2 buildings, with 1 RK, 1 BHK & 2 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from December 2027 to December 2029; 1 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 34% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

89 of the 136 units reported for sale are booked (65%); 1 phase has not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹9,200 per sq ft or less, counting balconies and terrace in the size. Buyers here paid a rate about 15% lower than the typical Maan rate in 2026. Most buyers paid ₹61–67 lakh for 2 BHK flats of about 660–850 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100048403 and P52100048413.Open MahaRERA and search P52100048403All projects in Wakad, Hinjewadi, Marunji