Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops, Jambhe

by Kolte-Patil Developers Limited. Jambhe, Pune 411057. View on Google Maps

Launched
4 years 11 months promised
Possession date (MahaRERA)
1 year 5 months awayPossession date unchanged since launch
Concrete structure (RCC)
75%Mid-constructionAverage across 4 buildings
Units booked
518 of 60386% booked
Price per sq ft (incl. balconies and terrace)
₹8,8002026 so far · 19 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK522
Other units (shops, offices or not given by type)81
Total units603
Buildings4
Land3.7 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 465 → 518 · structure 74% → 75% · final finishes 25% → 70%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
660 – 740 sq ft₹63 – 65 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹8,600 per sq ft332 sales
2025up 2% on 2024₹8,800 per sq ft38 sales
2026 so farabout the same as 2025₹8,800 per sq ft19 sales

Rate vs other Jambhe projects, 2026: about 10% lower

Compared with 6 similar projects in PIN 411057

Projects with 250–1,100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 11 mths4 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)March 2028December 2027
Concrete structure (RCC) complete75%92%
Share of units booked86%86%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 6 months of the promised 4 years 11 months have passed
Concrete structure (RCC) 75% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 33%Jun 2024: Excavation 75%Dec 2024: Excavation 75%Jun 2025: Excavation 75%Dec 2025: Excavation 75%Jul 2026: Excavation 75%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 48%Jun 2025: Concrete structure (RCC) 48%Dec 2025: Concrete structure (RCC) 74%Jul 2026: Concrete structure (RCC) 75%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 13%Jun 2025: Final finishes 13%Dec 2025: Final finishes 25%Jul 2026: Final finishes 70%Excavation 75%Concrete structure (RCC) 75%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
75%75%70%518
75%74%25%465
75%48%13%—
75%0%0%—
33%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops (MahaRERA P52100050599) is a residential project by Kolte-Patil Developers Limited in Jambhe, Pune 411057. It was launched in April 2023. It has 603 units in 4 buildings: 522 homes (2 BHK) and 81 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2028, unchanged since launch. Construction, averaged across its 4 buildings: excavation 75% complete, structure (RCC) 75% complete, final finishes 70% complete. MahaRERA records do not show it as ready to move in.

518 of its 603 units are booked (86%). Since the December 2025 update, 53 more units have been booked and the reported concrete structure (RCC) has gone from 74% to 75%. 80% of the 2026 (so far) sales we found here were at ₹8,800 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 19 registered sales. Buyers here paid a rate about 10% lower than at other Jambhe projects in 2026. Most buyers paid ₹63–65 lakh for flats of 660–740 sq ft.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension, or lapsed17
Under construction35
Possession date extended by the builder4
Typical time from launch to 100% structure3 years
Complaints on MahaRERA, all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050599.Check it on MahaRERA (P52100050599)All projects in Wakad, Hinjewadi, Marunji