Nyati Esteban II, Undri

by Nyati Realtors LLP. Undri, Pune 411060. View on Google Maps

Launched
3 years 11 months promised
Possession date (MahaRERA)
11 months awayPossession date unchanged since launch
Concrete structure (RCC)
49%Mid-constructionAverage across 5 buildings
Units booked
318 of 50064% booked

Project facts

2 BHK250
3 BHK250
Total units500
Buildings5
Land5 acres
Complaints on MahaRERA (filed by or against the builder)3

Since Dec 2025: booked 258 → 318 · structure 36% → 49% · final finishes 0% → 5% · complaints 0 → 3

Share on WhatsApp

Compared with 3 similar projects in PIN 411060

Projects with 250–1,000 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411060
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths3 yrs 9 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)September 2027June 2027
Concrete structure (RCC) complete49%85%
Share of units booked64%67%
Complaints on MahaRERA (filed by or against the builder)30

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years of the promised 3 years 11 months have passed
Concrete structure (RCC) 49% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 70%Dec 2024: Excavation 86%Jun 2025: Excavation 86%Dec 2025: Excavation 91%Jul 2026: Excavation 95%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 2%Dec 2024: Concrete structure (RCC) 14%Jun 2025: Concrete structure (RCC) 14%Dec 2025: Concrete structure (RCC) 36%Jul 2026: Concrete structure (RCC) 49%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 5%Excavation 95%Concrete structure (RCC) 49%Final finishes 5%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%49%5%318
91%36%0%258
86%14%0%160
70%2%0%95
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Nyati Esteban II (MahaRERA P52100053440) is a residential project by Nyati Realtors LLP in Undri, Pune 411060. It was launched in October 2023. It has 500 units in 5 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2027, unchanged since launch. Construction, averaged across its 5 buildings: excavation 95% complete, structure (RCC) 49% complete, final finishes 5% complete. MahaRERA records do not show it as ready to move in.

318 of its 500 units are booked (64%). Since the December 2025 update, 60 more units have been booked and the reported concrete structure (RCC) has gone from 36% to 49%.

Nyati's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA48
Completed without extending the possession date24
Completed after an extension, or lapsed12
Under construction12
Possession date extended by the builder6
Typical time from launch to 100% structure2 years 1 month
Complaints on MahaRERA, all Nyati projects32 (14 of 48 projects)

See all Nyati projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100053440.Check it on MahaRERA (P52100053440)All projects in Mohammadwadi, Undri